Search

E & I schedule

Forum Topic

Dear Members,  Kindly can anyone help me out in making a schedule for E & I project schedule which includes installation, commissioning and startup of control system in oil and gas field. Im new to this work and would like to have some help you guys....

Mar 19, 2018

Start dates in Gantt chart with baseline not on correct position

Forum Topic

Dear all,I have been searching for the answer to this question for couple days and did not find anything (it is driving me crazy!).When I insert both actual work/remaining work bars and baseline bars in Gantt chart, Start dates from actual work/remai...

Mar 21, 2018

Display link slope or the difference of two dates

Forum Topic

Hi, I'm fairly new to planning softwares but I get the basics of powerproject. My problem is that I can't display a column which shows link slope. Is it even posisible? There is a link loop but I ignored the link between these two tasks and now it do...

Mar 22, 2018

Duration % Complete not Rolling Up

Forum Topic

Hi Everyone, Can anyone suggest a reason why duration % complete isn't rolling up to summary level?My % complete type is the same for all activities, but I'm unsure what else to checkThanksEmma

Mar 22, 2018

DCMA 14 Point Schedule Metrics

Forum Topic

Hi,Wondering if anyone knows if  you can pull the DCMA 14 point assesmment info from a programme in Asta easily or at least elements of it.Any help would be appreciated.ThanksChris

Mar 23, 2018

Activity Weighting Parameter

Forum Topic

Hello Everybody, I hope you will be able to advice me regarding the following matter. I am working at the moment on a tender programme and I came across a special requirement from the client for the quality of the schedule which I have never met befo...

Mar 23, 2018

Building a Schedule No historical information

Forum Topic

Hello How would you go about building a reliable schedule when the project that you are planning is completely new. What are the requirement considerations, how would you break the scope of work, estimate resources durations costs etc.Any guidance / ...

Mar 26, 2018

Updating baselines with multiple open projects

Forum Topic

Hi All,I am having trouble understanding how the baseline updating works when multiple projects are opened at the same time. I want to batch export data on several projects. After opening all the projects, when I want to reassign the baseline, it onl...

Mar 26, 2018

Using two different resource rates in MS Project

Forum Topic

Hi there, I have a project where I want to track both cost and price within the task view Gantt chart. To explain a little more, each of my resources in the resource sheet has two rates, a standard rate, and then a sell rate which I have put into the...

Mar 27, 2018

Delay Duration and Reason capture in Primavera P6

Forum Topic

Hi,I am trying to setup a way in Primavera P6 to help capture all the delay related information, like delay reasons and durations. Delay Reason: I have come across "Delay Reason" activity code, but that will only allow me to provide a list of broad c...

Mar 28, 2018

EVM Work To Go formula

Forum Topic

My client would like me to provide % contingency left on the project with respect to BAC and EAC.The formula would then be (contingency remaining) / (work left to go)NowFor BAC, fomula would be (BAC - EV) for remaining work to go.For EAC, would the f...

Mar 31, 2018

Baseline changes and misrepresentation to Tribunal

Forum Topic

Hi Experts I need advice If someone alter changes in the Baseline programme knowningly and present the delay analysis based on the altered baseline to the Tribunal , what are the consequences for doing this. Actually i found all schedule has altered ...

Apr 1, 2018

Resources Labour units not recalculating after Loading

Forum Topic

Hi! I assigned some resource for trial, with its "Default Units/ time as 8/d" and then I assigned it to activities. After scheduling, the programme calculates the labour units based on that. (Pic 1) But then when I change the same resource "Default U...

Apr 2, 2018

Add column(s) to Revision Box

Forum Topic

Is it possible to introduce NEW column(s) into default Revision Box in page setup?  Thanks in advance.

Apr 4, 2018

Why not automatically closing old discussions?

Forum Topic

Once in a while a Planning Planet member revives very old discussions they should have asked years ago when the discussion was active.  It is offensive to many of us such actions.The following being the last one:http://www.planningplanet.com/forums/p...

Apr 4, 2018

Changing the order of activities

Forum Topic

Hi All,I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.Can anyone help me, i'm trying to simply re-order my activities? To explain what i've done so far:I have added in 3 activities, gi...

Apr 9, 2018

Changing the order of activities

Forum Topic

Hi All,I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.Can anyone help me, i'm trying to simply re-order my activities? To explain what i've done so far:I have added in 3 activities, gi...

Apr 9, 2018