Help!!! Duplicated Resources was not updated by using Baseline update utility in P6 8.2

D
David Cui 👤 Member for 10 years 11 months

Hi All,

I had a problem with baseline update in P6.

I am one activity in current schedule with the same resource assigned several times and Zero out some existing resources. I tried to update the baseline for this activity with changed resources. However, after updating the baseline using the following setting:

capture.png

 

The baseline budget is not updated properly and I saw that the existing duplicated resources in the baseline was only one of them left. This update actually removed the duplication. This is not what I wanted.

I would be very appreciated if someone have any solutions if anyone have suggestions?

Thanks for your help and I look forward to hearing from you.

David Cui

D
David Kelly 👤 Member for 21 years 7 months

I know everything about this.  Baseline Update has never worked, still has issues in version 17.12, but the issues change with each version. I still have a guide for doing this with version 8.3.  Send me your contact details and I will send you the PDF file....

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts