Changing the order of activities

Hi All,

I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.

Can anyone help me, i'm trying to simply re-order my activities?

 To explain what i've done so far:

I have added in 3 activities, given them a name and duration, applied logic to them and sceduled. Now i want to add a new activity inbetween activity 1 & 2?

Thanks in advance,

Charlotte

G
Gün Göksu 👤 Member for 21 years 2 months

Try to keep a gap of 10 (default) between the activity ID's if you intend to sort them by ActID (but you will quickly run out).

On the long term, consider using activity codes and sort through that.

You can sort by any column by clicking the column header.

A
Ahmed Sho 👤 Member for 8 years 1 month

Hi Charlotte
You can add more activities to the 3activities you have already just the way you added those 3activities in the first place highlight where you want to add another activity and click on the +sign on the right hand side and your activity will be added.
Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

it can be used just like excel if you click on the top of ANY column your data will be organized alpha numerically in an ascending  order. If you click it again it will be listed in an alpha numeric descending order

also under group and sort you can also tell it what oder that you want and can have more than 1. i.e. sort order by 

start 

 

activity id

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts