Manual excavation duration - 1 Cu. Mtr.
Forum TopicPlease suggest how much time it will take to excavate 1 Cu. Mtr. by a normal person?
Please suggest how much time it will take to excavate 1 Cu. Mtr. by a normal person?
Dear Planners If one of predecessors is not completed (out of sequence progress) using retained logic, start of successor activity is delayed until all of predecessors are completed. (Remaining early start date is delayed) It is required to track w...
Hello everyone, I would like to request if you would kindly participate in my questionnaire research that I am carrying out as part of an MSc Project Management dissertation at the University of Westminster. The survey will only take 5-7 mins of your...
I am new in Primavera P6. I built a schedule in Primavera, with activities from 18-Sep-2012 to 02-July-2014. I have its data date of 18-Sep-2012. But this schedule doesn't show critical activities as it should. It have large number of total floats, w...
Dear All,I am new on the FPSO Commissioning Schedule by Primavera P6 version 7.I need your help to send me any expamples for FPSO Commissioning Schedule with my graet Thanks to you.My E-Mail is "[email protected]"RegardsHanson
Dear All,I am new on the FPSO Commissioning Schedule by Primavera P6 version 7.I need your help to send me any expamples for FPSO Commissioning Schedule with my graet Thanks to you.My E-Mail is "[email protected]"RegardsHanson
Hi, I have been using Asta Powerproject for a few years now so I am quite familiar with the software. However, i am moving to a new company on Monday which they will be using Primavera p6. I have been watching video on Youtube about P6 and it makes m...
We think there's a gap in Milestone performance evaluation tools and have been recently working with Steelray to fill it http://ow.ly/yw1xb
Lads, Whats the different in terms of drying time for Lime Mortar and Portland Cement? Lets say its half brick thick and English Bond. I think as below, assume brick thickness is 65mm and mortar thick is 10mm. 1. Lime Mortar - 6 layers of brick / day...
I need to change the way that P6 distribute the budget cost.Its distribute the cost for each work hour ,for example if I have one activity start on 10 Apr.14 and finish on 10.May.14 the P6 will devide the cost of the activity to two parts , one in ap...
Hi all,Which is the best option to assign a resouce type for cost loading (labour, non-labour or material)? My intention to assign a cost loading resource (with unit rate 1/hr) fo all activites to develop the overall budget cost as per contract value...
Dear Planners,I have a schedule which I need to assign total cost of salaries (staff salaries), but the problem I am facing is that:1- In January I have total amount $9000 salaries2- In february I have total amount $ 9000 salaries3- In March I have t...
We've noticed a few issues importing XER files into Primavera P6, for example:Importing an activity where a resource is used more than onceRestoring a group of projects to a single destination projectLearn how to solve these issues http://ow.ly/yB1KE
The resource calendars are a mess and Im wondering if this is an issue as when an actual start date is entered to status the actvitiy the resource cost value is erased immediately? any ideas?
I have filtered WBS activities through a code. Now I want to add a WBS Activity to produce a activity bar for the duration of the 'Grouped by code' WBS activities.The problem is the WBS summary only follows the existing WBS it is attached, inorder to...
Hi Everyone, New to this forum and the Planning environment and I am desperate for some advice...I am 37, started working as a DOcument Controller last June at Olympic Park in Stratfordwith no prior experience within the construction sector in this r...
Hi everybody, I have a question about MS Project. I have a task that starts on 16.04.2014 and finishes on 26.06.2014.Start: 16.04.2014Finish: 26.06.2014Progress Data’s:Actual start: 29.04.2014Status Date: 29.06.2014Completion: %60 (Actual Start till ...
I am reviewing a schedule and found 2 activities connected with each other by a double relationship of SS & FF.. is this technically allowed? What is the effect on the logic? Kindly exfound. Thanks.
Here's why it's best practice to make schedule time buffer visible http://ow.ly/L8oU3064Pa5
Hi, Does any one can assit me with finding n solution for this error message. It is occured in P6 Glaboal schedule services - Publish Enterprise Summaries services. "2016-11-11 15:19:52:[TASK]:[PxEpsSpread]: [4] CORE(SQL): Errors occurred when execut...