I am reviewing a schedule and found 2 activities connected with each other by a double relationship of SS & FF.. is this technically allowed? What is the effect on the logic? Kindly exfound. Thanks.
Double relationship - Double trouble or playing football?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
This may apply to Column and Suspended Slab with Activities description as Columns & Suspended Slab.
Say Suspended Slab @ EL=+4.00 was casted yesterday, the columns @ EL=+4.00 and suspended slab @ EL=8.00 activities can now be started. The Activities for Forwmworks for Suspended Slab @ EL=8.00 may wait for some Columns to be started in order to commence but the Suspended Slab @ EL=8.00 can never be completed unless all Columns are completed.
Susp Slab SS+3d with columns
Slab FF+6d with columns
Although in some cases Suspended Slab may not need to wait for some columns to be started becasue Scaffoldings used for the safety purposes in casting of columns will be retained to be used for the slab formworks. Therefore Suspended Slab activities can start once predecessor slab already casted.
For Activites with a deeper details such as Formworks for Columns @ Grid 1 & 2, Grid A-M, Rebars for Columns @ Grid 1 & 2, Grid A-M, Laying of Scaffolding along Grid 1 & 2, Grid A-M, Casting of Concrete for Columns @ Grid 1 and so on.... the required Link is only FS.
Hi Mike,
Thanks for the reply. Is there a reason why? what is the effect on the logic? AS I observe, the successor's FD will adjust automatically when the activity is delayed, even if the successor has already actually started. That means its realistic. Otherwise, if SS only was sued, the successor will not be affected if the activity will be delayed.
Pio
Hi Pio
It is not allowed - SS FF Links should never be used in a construction programme.
Best regards
Mike Testro