Wembley Stadium Failure
Forum TopicHi All, Just a quick query - can anyone point to some literature or journals which discuss the nature of the project management of the Wembley National Stadium development?Regards,DC
Hi All, Just a quick query - can anyone point to some literature or journals which discuss the nature of the project management of the Wembley National Stadium development?Regards,DC
I recently told that there is a International Construction Norm for the Civil Construction of a Steam Turbine Table but I find that almost impossble to believe since the designs and constructability vary based on the size of the proposed Stator Unit....
We have an installation of P6 R8.2 EPPM (for Web client) server on Microsoft Server 2008 with WebLogic 11g. The Database installed is MS SQL Express 2005. Java JDK 6 update 27 was selected during P6 setup.P6 installed and configured without errors ...
We have an installation of P6 R8.2 EPPM (for Web client) server on Microsoft Server 2008 with WebLogic 11g. The Database installed is MS SQL Express 2005. Java JDK 6 update 27 was selected during P6 setup.P6 installed and configured without errors ...
Hello All Planners.Please have a look at following example;I added a Material Resource Named "Crushed Aggregates" in my schedule.I have changed resource type to "Material" and adjusted the price per unit.No the unit of measure that i want to keep is ...
Updating in progress activities in Primavera Contractor. is there an easy way to update in progress activities without having to trial and error a % complete. I just want to progress the works as planned. I know there is the update progress optio...
I have milestones within my programmes which represent capital approvals meetings. These meetings are monthly so I have created a calendar for these milestones with only 1 working day per month. If the activities preceeding these milestones are late,...
Dear all; kindly not that I face an error in expedition it come into view only when importing to excel the module of Corr. Sent; a window appeared as follows: [[wysiwyg_imageupload:957:height=182,width=350]] load_error.png Please feedback with th...
Hi dear all,Please can anyone help me. How can I change primvare default fonts to local fonts(Azerbaijani).How can I use local fonts in primavera.I'm using P6 R8.2. Regards,Mikayil.
Dear Scheduler...I have project 4000 activities and with TF = -117 in the current schedule NOT baseline, because we already late and behaind the schedule. My PM he want me to reduce the -ve TF before we submit it to the owner. So, any suggestions?Tha...
i have started a new project and the owner wants to change the start date for working day calculation. I want to movethe start date and the activies to an earlier date.
The AACEI RP 29R-03 2011 on the modeled substractive methods provide for extraction of entire activities or a portion of the as-built durations representing delays or changes from a network analysis model representing the as-built condition of the sc...
Dear Schedulers,As you know for the Construction project the WBS parents (level 2) should be as below then (level 3)...1-Milestones2- Pre-Construction 3- Design4- Procurement5- Construction6- Contract CloseoutSo, how it's going to be for the Oil and ...
Dear All, What is the easiest way to show the progress bar against the baseline? Regrads,
Friends Please help me in the term Man hour efficiency..Please let me know the formula if any body knows... RegardsArun V
Hi Friends, Kindly help me in the issue of generating the rollup summary in the WBS for the UserDefined fields. Thanks & Regards Suresh KJ
Hi Guys,We've just completed a review of Full Monte which is a cost and schedule risk analysis add-on to Microsoft Project. You can read it here http://bit.ly/wnMkPoI hope this is useful,Emily
Hi Guys,We've just completed a review of Full Monte which is a cost and schedule risk analysis add-on to Microsoft Project. You can read it here http://bit.ly/wnMkPoI hope this is useful,Emily
Hi Guys,I have P6 Optional Client and EPPM working fine on my laptop and I was trying to get the iPhone app (P6 Team Member) to connect to it. The documentation has no examples of what the URL might look like and I was hoping someone here could help ...
Hi, I am on a steep upward learning curve with P6 and need some help. My client wants all activities resourced, which I have done. He also wants a spend profile for the scheme. We are not generating our cost information at activity level, but have se...