Updating in progress activities in Primavera Contractor.

T
TONY SEWELL 👤 Member for 15 years 9 months

Updating in progress activities in Primavera Contractor.

 

is there an easy way to update in progress activities without having to trial and error a % complete. I just want to progress the works as planned.

 

I know there is the update progress option but this then schedules the whole thing when you do it, I just want to record as-built up to data date before scheduling, similar to how activities are progressed without scheduling when you tick finished box.

 

Thanks

 

Tony

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Tony,

There is a way, provided all activities are on schedule. You can drag the data date to your new cut-off date and this will highlight (yellow) all activities scheduled within that period and then choose update progress and this will update all highlighted activities as per plan.

Regards,

Daniel

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts