Assigning a Material Resource in P6

S
SM PUM 👤 Member for 14 years 7 months

Hello All Planners.

Please have a look at following example;

I added a Material Resource Named "Crushed Aggregates" in my schedule.I have changed resource type to "Material" and adjusted the price per unit.No the unit of measure that i want to keep is "Cu.m".The issues that i am facing are,

1- I am not able to find an option to make my resourse loading a "spread loading" i.e, I want to tell primavera tha 1000 C.m of crush is required for a certain activity in 2 weeks.The only way i find is assigning price per unit and then if i assign this esource to the activity,then it multiplies the price per unit with the duration,that i do not want.

I want to give my resuorse a certain price and qty that should be spread on total duration of activity.

 

I hope my question is clear.Like in primavera Risk analysis there is option of "spread loading " and "point loading".

If not then how you assign material resource to your activities.please guide.

 

Thanks

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts