Time claim filter problem

Forum Topic

Hi, all I'm sorry my spelling mistakes. I am not god at english I am going to filter my special activity's all successor chained by to each other but I didn't find anyway For example I should remove my fancoil activity and all successor's(path) aktiv...

Aug 3, 2016

Actual Units Update Issue

Forum Topic

While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press ...

Aug 3, 2016

Baseline for Road projects

Forum Topic

Dear sir/madam,I have worked in some of the high rise building projects in middle east.I really like to learn about the baseline of the infrastructural project based in middle east.Therefore,Can any one help me by providing a sample baselines of infr...

Aug 3, 2016

Ask Mike T - New Service

Forum Topic

Hi EveryoneI have a new tab on my website - www.expertdelayanalyst.com - Ask Mike T.If you have a question on Delay Analysis or Planning matters I will do my best to answer it - free of charge.Best regardsMike T.

Aug 3, 2016

Software TILOS

Forum Topic

donde puede descargar el programa TILOS con su crack

Aug 4, 2016

Change start time and finish time (hours and minutes)

Forum Topic

Hi All.My query to end this week is the most difficult to resolve. I have  figured out the issue but failed to fix it.My program is based on weeks and days, however when viewing the time (hours and minutes) format. My project start and finish links a...

Aug 4, 2016

Progress marking

Forum Topic

Hello everyone,I have a problem with progress marking.I established a programme. Some of the bars are flying a year back when I input progress information onto associated activity.I check the links and restraint flags. everything seems normal.I hope ...

Aug 4, 2016

Test Your Case

Forum Topic

So you think you are entitled to an Extension of Time?I have developed a short excel list of question which - when answered honestly - will test the strength of your case. Ping me at [email protected] for a free trial.Best regardsMike Testro

Aug 5, 2016

Estimating Activity duration in building project

Forum Topic

Dear members; I have a question regarding estimation of activity duration by using productivty rates; as i understand the formula for Duration = work quantity/(production rate X resource usage)Now; i have a activity say Plaster works with quantity 20...

Aug 6, 2016

Right Logical Relationships

Forum Topic

Dear All,May be it seems stupid to ask this question but still i will prefer to ask.In construction schedules, most of the activities go parallel. What logic do you people prefer while doing your schedule.It is very difficult to make whole schedule o...

Aug 7, 2016

How to display Resource Histogram by Month with Men Required

Forum Topic

 Hi, In the Resource Usage Profile I am trying to display the histogram by Month with the number of men shown down the left hand side rather than the hours for the month.I display the columns by Month by setting the Timescale to Quarter/Month.I then ...

Aug 8, 2016

Why Project Calendars Are Preferable to Global Calendars

Forum Topic

Global calendars appear to be the way to go when creating a new calendar definition. But there are sound reasons for defining a calendar limited or restricted to a specific project http://ow.ly/lhpo3031MsP

Aug 8, 2016

Lag ,Total Float and Duration

Forum Topic

Dear Family MembersWhat is the maximum and minimum Lag allowed in a program??What is the maximum Activity duration can be allowed in a program??What is the maximum and total float allowed in a program ?? RegardsArun.V

Aug 8, 2016

Multiple Overtime Factors

Forum Topic

Hi,We are looking at cost loading our schedules, but we have hit a snag in that our operatives are paid an overtime factor of x1.5 on Saturday mornings, and a factor of 2.0 on Saturday Afternoon->Sunday .Is there a way of specifying different rates f...

Aug 8, 2016

P6 Remaining Units not equal to Budgeted Units

Forum Topic

Hello, I'm assigning resources to activities on my plan and as the project has not started yet I would expect the remaining units to be the same as the budgeted units. So basically if I have a 5 day duration activity and the resource will work 20 hou...

Aug 9, 2016

Resource Assignments (At completion units)

Forum Topic

Dear Frndswhile updating the programm (At completion units) will be change. how can i fix it?can you explain me details?i am waiting your valuable reply.Thanks.....

Aug 9, 2016