Dear sir/madam,
I have worked in some of the high rise building projects in middle east.I really like to learn about the baseline of the infrastructural project based in middle east.Therefore,Can any one help me by providing a sample baselines of infrastructural projects like roads,bridges,sewage systems etc?Please be kind enough to give me in XER file,then I can easliy understand the relationships of each activities.
Please be kind enough to email me- [email protected]
Dear sir,
Here,in Middle East.they use only Primavera in order to prepare the baseline.So ,Can you give me a sample baseline to refer?
Mike,
Line of Balance is just another way to present project schedule. So linear projects may be modeled using P6 or other tools.
Though Line of Balance presentation of project schedules exists in Spider Project since 1996 we never state that it is the only way to present linear project schedules.
Best Regards,
Vladimir
Hi Mohamed
P6 is not suitable for linear projects - you need to look at a Time - Distance software such as Tilos. Asta PowerProject also has a similar facility with its Line of Balance system.
Best regards
Mike Testro