Progress marking

T
Tolga Taluy 👤 Member for 10 years 11 months

Hello everyone,

I have a problem with progress marking.

I established a programme. Some of the bars are flying a year back when I input progress information onto associated activity.

I check the links and restraint flags. everything seems normal.

I hope someone help me with this.

thank you in advance.

C
Charlotte Underhill 👤 Member for 9 years 11 months

Hi Tolga,

 

Have you checked the date of your progress line? If you progress a task and reshedule the progressed task will jump back behind the progress line.

Regards,

 

Charlotte