Search

Best Method

Forum Topic

Hi all, Which do you think is the best way to get PMP certified?Is self study better or though training centres?   Kamran

Aug 16, 2011

Date formats while exporting from P6

Forum Topic

How can i control the date formats while exporting start dates from P6 to excel. When I am exporting in excel the format is appearing as m/d/yyyy but when my collegue exporting the format appearing is dd/mm/yyyy   How I can ensure everybody will have...

Aug 16, 2011

Restore Base line

Forum Topic

Dear friends Please guide me how to restore the base line program from the updated program. I made a big mistake .I prepared the base program and updated with base prgram as current project .I did nt mmake a single copy or back up of the base program...

Aug 17, 2011

Resource pool- WILL NOT SAVE!!! LOSES ALL LINKS??

Forum Topic

Hi guys Master Project = PROJECT # 1, HOLIDAY, and OFF SITE VISITS Individually, all of the resources have been set up to share resources in a file named 'resource pool' when you view resource usage and all the files are open.... the resources are li...

Aug 17, 2011

Resourse loading

Forum Topic

Dear Friends In the base program I have an activity of Floor Slab Casting I have given the activity duration as 7 days and the calendor used is 7 day calendor . For resouse loading I have to use Materials & Labour & Non labour (Machineries) Labor Shu...

Aug 17, 2011

PRA 8.6: Why do Oppty Hammocks cause zero TF?

Forum Topic

  Background:  PRA V8.7, using opportunities within the risk register of PRA My PM wants an explaination why an activity (that contains an oppty node) with 1.5yrs probilistic float has a100% critical index. From what I can see it is the hammock off t...

Aug 17, 2011

using - lag

Forum Topic

Hi Everyone                        Is it a good practice to use - lag  in a programme.could any of you guys please tell me the drawbacks of using negative float.  Thanks Sach

Aug 17, 2011

VBA

Forum Topic

Hello planners,   I am using VBA in PowerProject (v 10.0.04) to import tasks and allocations from a csv-file. I am using SetUserStart and SetUserEnd (from the PermanentDemandAllocation class) to set the start- and enddate of the allocation, but I wou...

Aug 17, 2011

% weightage calculation

Forum Topic

Could anyone confirm me regarding the % weightage calculation.i heard from some planner that you can calculate % weightage based on duration assigned for the activities to prepare s curve and track progress. Does it works sometime?According to me for...

Aug 18, 2011

Need your advice

Forum Topic

Hello i 'm working to prepare a file for new great project i'm making  level-3- and s curves and histogrames . I need your advice for my work . i will seend to you my work and we will send to me your commantaires. this my email :sehari.mohamed@gmail....

Aug 18, 2011

Phase Value roll-up

Forum Topic

Why in order to get the correct phase values roll-up, when Phase value is the sum of activity values, I must click F8 after formula execution? I was expecting for the value be computed automatically whenever a value is changed no matter if manual or ...

Aug 18, 2011

PowerProject link to Excel

Forum Topic

Hi,   Is it possible to link PowerProject (v10/v11) to Excel, whether this is via VBA or an external 'middle' programme, if so is there some api's we can use? Thanks

Aug 19, 2011

Activity Usage Profile - Hour by Hour

Forum Topic

Hello All,Is it possible to get an hour by hour resource distribuition in P6 ? I have prepared a shutdown programme which is resourced at an activity level but when I switch to activity / resource usage profile it seems to accumulate effort / unit on...

Aug 19, 2011

p3 durations

Forum Topic

i have created a p3 schedule with 250 activities the schedule is currently set to duration in days the problem is there are 3 times during the project where a shutdown must occur and you have a 6 hour max window to complete all tasks so our activitie...

Aug 19, 2011

EV Cost and Schedule Indicators

Forum Topic

Hi, I have developed a schedule that is resource loaded with cost entered for the standard rates per hour for the respective resource. It is baseline,tracked and updated to date. In the calculation tab along with the task information for EV calculati...

Aug 19, 2011

Weekend puzzle -Lateral thinking word games

Forum Topic

Can you name these 9 words or phrases?   You may find these a bit difficult if english is not your native language.     [[wysiwyg_imageupload:634:]]

Aug 19, 2011

P6V7 Project Acess Mode - Please help

Forum Topic

Hi,   I need you help please..   I am using P6v7, Stand Alone Version.  1. I cannot  access my project on an exclusive mode... although I have "Superuser" profile/Privilage. I cannot open the project on an exclusive mode:   File>Open>Project (exclusi...

Aug 19, 2011

P6V7 Project Acess Mode - Please help

Forum Topic

Hi, I need you help please..   I am using P6v7, Stand Alone Version.   1: I cannot access my project on an exclusive mode... although I have "Superuser" profile/Privilage. I cannot open the project on an exclusive mode: File>Open>Project (exclusive m...

Aug 19, 2011

Project Resource Analysis

Forum Topic

Hi Everyone, I am about to start a position that focuses on project resource analysis.  I have a lot of project management experience, but never specified in project resource analysis.  Can anyone recommend some resources or topics I should go over? ...

Aug 19, 2011