VBA

Hello planners,

 

I am using VBA in PowerProject (v 10.0.04) to import tasks and allocations from a csv-file. I am using SetUserStart and SetUserEnd (from the PermanentDemandAllocation class) to set the start- and enddate of the allocation, but I would also like to set the allocation percentage. But I can't find that specific member.

 

Does anyone know if it is possible to change the allocation percentage using VBA?

 

Thanks in advance!

 

 

Kind regards,

 

Marinus

A
Andrew Willard 👤 Member for 16 years 5 months

Hi Marinus,

You can't progress a demnad allocation. The allocation needs to be of type permanentscheduledallocation. You can then set the effort percent complete

 

Regards

 

Andrew

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts