Changing Activity type for 3000+ Activities
Forum TopicWhat is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1Thanks
What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1Thanks
What is the fastest way to change over 3000 activities from resource dependent to task dependent? P6 V8.1Thanks
Please help - I'd like to connect to the Oracle XE PMDB through an ODBC connection but I get the following errors:1) Unspecified Error:Source: Microsoft OLE Provider for ODBC DriversDescription: [ATI] [OpenRDA ODBC] RDA Error; resource not available ...
The client is organizing a bi-weekly Schedule Review Meeting. The proposed invitees are the planner, the project controls manager, and the project manager from the client side. On our side, we have the project manager, the project controls manager, t...
Hi all - ANY advice would be very much appreciated,,, I am currently running imports into P6 (from an xls workbook) that give me both Activities and Resource Assignments, my question is this – is there a method of OVER-WRITING the resources during th...
Have a question on deleting activities from P6 after those activities have been baselined, or multiple baselines. Once an activity is baselined, or is baselined multiple times for variance analysis, on a bi-weekly basis, and this activity is no longe...
Hi Guys, Has anyone out there had any experience with integrating the schedule with the estimate. My organisation currently works with an estimating depatment that goes off and builds an estimate (they use expert & or Candy) at the same time we have ...
By Default, In Primavera P6, we get Mon, Tue, Wed, Thr, etc for Timescale setting Week/Day1 (Under Option “Show Primary Dates”). How to get numeric date value in this week/day1 setting like 7,8,9, 10 of May or June, etc? If we use Option “Show Ordina...
Dear all,Can any one give the standard productivity for Railing works in KG.Thanks & RegardsSankar Vijayan
hi all, some of my colleagues use P6 v6.2.1 daily.they've got a "server" (which is actually a common XP workstation) with P6 and SQL server express installed.opening the server database from the various workstations isn't a problem, and it all works ...
I get this error when I try to import an XLS into 8.2 Professional Client: ERROR: control_updates_flag is null for TASK ActivityID: 1.1A It seems that this field is an indicator that determines whether the activity status updates made in Team Membe...
Hi,If you can, please give me some advice regarding this Delay Analysis Problem. I used “Impacted As Planned” method to analyses delays.For the very first delay Event, I just took the Baseline & Impact the Delay into that. Now, my Problem is for the...
Hi Knowledgeable professionals,Please should all milestones be gathered under a unique WBS (e.g. a WBS named "Milestones and Keydates") or should it be inserted within the WBS containing the deliverable that is related to the milestones (e.g. Engine...
Hi, I am a student at Dakota State University and I am currently taking a class on project management. I was wondering if I could have someone who is a project manager answer a few general questions about your job for an assignment. Please reply if ...
We're currently in the process of getting a baseline approved by the client, and would like to better understand how others get around the use of constraints. Presently we have no constraints in the schedule, but have placed certain activities into t...
I have just updated my P6 V8.1 Professional and Optional Client book to Version 8.2. I also sell a PowerPoint slide show to accompany the book to organisations that wish to run their own training courses. This material is PMI accredited so training o...
HiCould please any one help me in set up a profile for productivity? Assumed we do have a TBM and the ground profile, could be possible to assign TBM productivity based on the ground, so that nay delay will be reflected in the re-scheduling? If you d...
Sir I have a problem with displaying negative floats in my project during progress updation. I have put a must finish contraint to the activities. But activities whose actual start and actual finish are entered does not display negative float, though...
Hi Guys, We all encounter conflicts on projects at some time. Don’t shy away from conflict: embrace it and manage it. Your team will thank you for it! Here's 5 tips for dealing with conflict on projects http://bit.ly/GEhFXO I hope you find this helpf...
Hi Guys, We've just posted a tutorial on Getting to know Deltek Cobra 5.1 designed for folks who are new to Cobra. It also has a 13 minute video tutorial as well. Here's the link http://bit.ly/GEjaW1 I hope this help, Emily