Delay Analysis using Impacted As Planned Method

Hi,

If you can, please give me some advice regarding this Delay Analysis Problem.  I used “Impacted As Planned” method to analyses delays.

For the very first delay Event, I just took the Baseline & Impact the Delay into that. Now, my Problem is for the Next Delay event, should I use the Baseline or Already Impacted Programme to demonstrate the Delay Analysis.

Thank You

M
Mike Testro 👤 Member for 20 years 6 months

Hi Prageeth

You should impact your delay events in strict chronological order of date of impact using the same chart in a rolling sequence.

The date of impact is the last date that the impacted activity could start after the event has run its course.

Bear in mind that the Impacted As Planned method as described in the SCL protocol 2002 is not to be used for Forensic Delay Analysis but only for Work in Progress.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts