Resources Labour units not recalculating after Loading

Forum Topic

Hi! I assigned some resource for trial, with its "Default Units/ time as 8/d" and then I assigned it to activities. After scheduling, the programme calculates the labour units based on that. (Pic 1) But then when I change the same resource "Default U...

Apr 2, 2018

Add column(s) to Revision Box

Forum Topic

Is it possible to introduce NEW column(s) into default Revision Box in page setup?  Thanks in advance.

Apr 4, 2018

Why not automatically closing old discussions?

Forum Topic

Once in a while a Planning Planet member revives very old discussions they should have asked years ago when the discussion was active.  It is offensive to many of us such actions.The following being the last one:http://www.planningplanet.com/forums/p...

Apr 4, 2018

Changing the order of activities

Forum Topic

Hi All,I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.Can anyone help me, i'm trying to simply re-order my activities? To explain what i've done so far:I have added in 3 activities, gi...

Apr 9, 2018

Changing the order of activities

Forum Topic

Hi All,I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.Can anyone help me, i'm trying to simply re-order my activities? To explain what i've done so far:I have added in 3 activities, gi...

Apr 9, 2018

Font and design tools not appears on Page Setup window

Forum Topic

Hi all!Font options and design functions are not appears for some users on Primavera 8.2 . I am looking for the solution. This a picture from web. I mean the tools under Add text section. I hope I could explain. How can i solve this problem?[[wysiwyg...

Apr 12, 2018

Resource Profile Curves for Oil & Gas FEED Projects

Forum Topic

Greetings,I have been working on and wanted to know from your experience that which resource profile curves (either P6 default or customized such as deliverable or discipline specific) works best for Oil & Gas FEED projects, so that the overall Engin...

Apr 14, 2018

Resource usage in a report

Forum Topic

Dear All,In a report I have included a table showing the tasks that a resource should be working on in a particular week. So open tasks per week per resource.When possible I would like to extent that table with the amount of hours a resource should b...

Apr 16, 2018

Microsoft Project Updating - 2 Weeks Only

Forum Topic

Hi All, My boss has asked me to provide an update of project porgress for a 2 week timeframe only. This would range from the status date + 2 weeks. When using the 'date range' filter it shows activities that start in this timeframe and finish after i...

Apr 16, 2018

primavera budgeted cost changes

Forum Topic

Hi All,i assigned resources and cost to  my schedule ... but when i enter any actual date in the schedule budgeted total cost gets zero ..before i didnt come across with this kind of situation.. your help will be appreciated.. thanks ina dvance

Apr 16, 2018

The Data-Driven Approach to Project Risk Management

Forum Topic

The data-driven approach to project risk should be:  Collecting better and more targeted data and informationDeveloping a more accurate risk ranking systemEstablishing a stronger understanding of project risksDeveloping more relevant metrics, rather ...

Apr 17, 2018

Contemporaneous and Forensic Time Impact Analysis

Forum Topic

hello expertsI'm confused about differences between "Contemporaneous Time Impact Analysis" and "Forensic Time Impact Analysis". can anyone explain me what are the differences between these two topic?

Apr 17, 2018

Baseline versus Actual Schedule Duration Complete Comparison

Forum Topic

Hello,I need to compare Baseline Duration %Complete versus Actual Duration % Complete. I know that I can see this with "Schedule % Complete" column at activity level, not WBS Level. Schedule % Complete uses EV data for WBS. But what I need is to comp...

Apr 18, 2018

Change Order Impact Study

Forum Topic

Hello,In my project I've "revised baseline" Dated 31-05-2017 and "recovery schedule" Dated 20-01-2018, updates are applied on the recovery schedule. Now, I've few change orders that I need to study thier impact and decide the EOT the Contractor deser...