Search

Career

Forum Topic

URGENT Looking For "Primavera Planner" Female with 5 years' experience in dredging, marine construction and reclamation.Send your CV to : [email protected]

Dec 7, 2015

Labor units

Forum Topic

Hi, When I'm assigning resources on activities the entrie unit is appearing on the first day itself. I mean an activity with 10 days duration when assignning 1000 labor units it should equally distribute during the working days. If it is seven day wo...

Dec 7, 2015

Labor units

Forum Topic

Hi, When I'm assigning resources on activities the entrie unit is appearing on the first day itself. I mean an activity with 10 days duration when assignning 1000 labor units it should equally distribute during the working days. If it is seven day wo...

Dec 7, 2015

Subcontractors as resource

Forum Topic

Please help... So I went ahead and set up all of my activities with dates, predecessors, successors etc for a project which is a construction contract where I have some of the work that is self performed, some where I have vendors providing materials...

Dec 7, 2015

Subcontractors as resource

Forum Topic

Please help... So I went ahead and set up all of my activities with dates, predecessors, successors etc for a project which is a construction contract where I have some of the work that is self performed, some where I have vendors providing materials...

Dec 7, 2015

Why "Fragnet"

Forum Topic

Good Morning AnalystsI dislike the term "Fragnet" used by some analysts to describe a series of events inserted into a barchart to represent delaying events.Why Fragnet - is it supposed to a connection of "Fragmented Network"? If so then why so?I sus...

Dec 8, 2015

Primavera P6 wandering Baselines

Forum Topic

Hello, I was just wondering if anyone could help me.  I am working on a number of programmes / schedules within Primavera P6.  All of which have baselines.  I have set the Project and Primary baselines within 'Assign Baselines', but every now and the...

Dec 8, 2015

Primavera P6 wandering Baselines

Forum Topic

Hello, I was just wondering if anyone could help me.  I am working on a number of programmes / schedules within Primavera P6.  All of which have baselines.  I have set the Project and Primary baselines within 'Assign Baselines', but every now and the...

Dec 8, 2015

Primavera P6 wandering Baselines

Forum Topic

Hello, I was just wondering if anyone could help me.  I am working on a number of programmes / schedules within Primavera P6.  All of which have baselines.  I have set the Project and Primary baselines within 'Assign Baselines', but every now and the...

Dec 8, 2015

Delay resource assignment

Forum Topic

Hello PPlanners and SP users,I cannot find how to make a resource to start later than the activity start date;for example, Activity A is 2 week long, Resource 1 will work 10 days, Resource 2 will only work the last 3 days;Resource 1 and Resource 2 ar...

Dec 8, 2015

Monitoring Remaining Planned Costs

Forum Topic

Hello everyone,I have a question regarding planned costs for future periods.Example (please correct my procedure if i do something wrong):At start: Activity with original duration of 2 months costs 1000.Planned cost by default is Month 1 - 500, Month...

Dec 8, 2015

Planning engineer Vs Site engineer

Forum Topic

 hi, Im a Planning enginner and i have experience one year in planning (P6) but i dont have the site experience , and now i got an offer to be a site engineer in the same company.i think site engineer better coz for the future can be a project manage...

Dec 9, 2015

kl

Forum Topic

ikl

Dec 9, 2015

Multiple projects for each part of project

Forum Topic

Hi any help appreciated with this. I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project. Obviously there linked between and I can open all at once but are there any differ...

Dec 9, 2015

Multiple projects for each part of project

Forum Topic

Hi any help appreciated with this. I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project. Obviously there linked between and I can open all at once but are there any differ...

Dec 9, 2015

Multiple projects for each part of project

Forum Topic

Hi any help appreciated with this. I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project. Obviously there linked between and I can open all at once but are there any differ...

Dec 9, 2015

Multiple projects for each part of project

Forum Topic

Hi any help appreciated with this.  I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project. Obviously there linked between and I can open all at once but are there any diffe...

Dec 9, 2015

EAC Calculation using CPI

Forum Topic

I'm using the formula for EAC:EAC=AC+ ((BAC-EV)/CPI) My question is, do I calculate my EAC for each activity and sum it up to the WBS or project level, or do I use the calculated CPI at the project level and calculate it there.  

Dec 9, 2015

EAC Calculation using CPI

Forum Topic

I'm using the formula for EAC:EAC=AC+ ((BAC-EV)/CPI) My question is, do I calculate my EAC for each activity and sum it up to the WBS or project level, or do I use the calculated CPI at the project level and calculate it there.  

Dec 9, 2015