Labor units

Hi,

When I'm assigning resources on activities the entrie unit is appearing on the first day itself.

I mean an activity with 10 days duration when assignning 1000 labor units it should equally distribute during the working days.

If it is seven day working calendar then it should be 100 units / day.

But in my case it is appearing 1000 units on the first day and 0 units on the remaining 9days.

Can anyone help me fix this problem.

By
Abilash

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts