Hi any help appreciated with this.
I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project.
Obviously there linked between and I can open all at once but are there any differences or anything I need to watch out for dealing with this multi project for 1 project?
an advised way of putting all into 1 would be appreciated, I was going to create a new one, create a wbs and open all in 1 then move out of each project into new wbs.
any comments appreciated
Hi,
Open all at once and Merged all WBS in One Project. Make sure when using Copy Paste, Under Relationship, Uncheck the Box "Only Between Copied Activities"
Hope this will help