Search

Cleaning schedule relationships

Forum Topic

Hi planners,I have a schedule which contains many unnecessary relationships that I have to remove.I started with the following case : if I have 3 activities A, B & CA --- FS---> BB --- FS---> CA --- FS---> C ( I have to remove the third relationship)...

Mar 14, 2012

As late as possible constraint

Forum Topic

Hi,Currenlty carrying out a tidy up operation on a BAeline programme prior to a delay analysis.My question is how would you deal with a set of activities that have no predecessor and have an 'As late as possible' constraint assigned to them??Thanks i...

Mar 14, 2012

Pert view

Forum Topic

Hi planners,What is the best planning software showing clearily the activity network to be able to trace schedule logic easily?I have tried the timescaled Logic diagram in P6.7 but I believe that we can find better in term of presentation.Many thanks...

Mar 14, 2012

MSP2007 - Showing Progress within Summary Bar

Forum Topic

I've seen a few posts on similar subjects on PP and through searching the internet, but not seen a reply that works for me (as yet!!). When I used MSP2003, I could set up a "Summary Progress" bar that superimposed itself over the "Summary Bar". Howev...

Mar 14, 2012

ERP Oracle

Forum Topic

Dear AllHow to get  trial copy from ERP ORACLEalso i need tourtial for these software

Mar 15, 2012

PM6 v7 ODBC connection error

Forum Topic

Please help - I'd like to connect to the Oracle XE PMDB through an ODBC connection but I get the following errors:1) Unspecified Error:Source: Microsoft OLE Provider for ODBC DriversDescription: [ATI] [OpenRDA ODBC] RDA Error; resource not available ...

Mar 15, 2012

Schedule Review Meetings

Forum Topic

The client is organizing a bi-weekly Schedule Review Meeting. The proposed invitees are the planner, the project controls manager, and the project manager from the client side. On our side, we have the project manager, the project controls manager, t...

Mar 16, 2012

Importing Resource Assignments

Forum Topic

Hi all - ANY advice would be very much appreciated,,, I am currently running imports into P6 (from an xls workbook) that give me both Activities and Resource Assignments, my question is this – is there a method of OVER-WRITING the resources during th...

Mar 16, 2012

Delete or Not to Delete Activities in P6

Forum Topic

Have a question on deleting activities from P6 after those activities have been baselined, or multiple baselines. Once an activity is baselined, or is baselined multiple times for variance analysis, on a bi-weekly basis, and this activity is no longe...

Mar 16, 2012

Integrate P6 with Esimate

Forum Topic

Hi Guys, Has anyone out there had any experience with integrating the schedule with the estimate. My organisation currently works with an estimating depatment that goes off and builds an estimate (they use expert & or Candy) at the same time we have ...

Mar 17, 2012

Productivity for Railing works

Forum Topic

Dear all,Can any one give the standard productivity for Railing works in KG.Thanks & RegardsSankar Vijayan

Mar 19, 2012

error code DSECL-0549-F (disconnected from database)

Forum Topic

hi all, some of my colleagues use P6 v6.2.1 daily.they've got a "server" (which is actually a common XP workstation) with P6 and SQL server express installed.opening the server database from the various workstations isn't a problem, and it all works ...

Mar 19, 2012

8.2 XLS Import Error

Forum Topic

I get this error when I try to import an XLS into 8.2 Professional Client:  ERROR: control_updates_flag is null for TASK ActivityID: 1.1A It seems that this field  is an indicator that determines whether the activity status updates made in Team Membe...

Mar 19, 2012

Delay Analysis using Impacted As Planned Method

Forum Topic

Hi,If you can, please give me some advice regarding this Delay Analysis Problem.  I used “Impacted As Planned” method to analyses delays.For the very first delay Event, I just took the Baseline & Impact the Delay into that. Now, my Problem is for the...

Mar 19, 2012

Milestones and Key dates WBS

Forum Topic

 Hi Knowledgeable professionals,Please should all milestones be gathered under a unique WBS (e.g. a WBS named "Milestones and Keydates") or should it be inserted within the WBS containing the deliverable that is related to the milestones (e.g. Engine...

Mar 19, 2012

Project Manager? I need your help.

Forum Topic

Hi, I am a student at Dakota State University and I am currently taking a class on project management. I was wondering if I could have someone who is a project manager answer a few general questions about your job for an assignment.  Please reply if ...

Mar 20, 2012