Delay Analysis or Time Impact Analysis (TIA)

Forum Topic

Hi Planners,   I need your advise for this matter. The Contractor has been lapsed for their Contractual completion date but the project remain incomplete (XX% complete) which difinitely requires Extension of Time to complete the outstanding works. Th...

Nov 28, 2010

Excel Export & Import Issues

Forum Topic

Hi to all I exported a program P6 in XL format to workout resources,when i imported back to primavera ,it displayed 'system is running out of memory ,close other applications and carry the operation again 'Is there any solution to fix the problem 

Nov 28, 2010

Claims based on specifications

Forum Topic

good morning to all planners in the world There is condition in the specification in the contract, forced us to submittal inspection request to anything to QC department of supervisor before 24hr, for example if we want to submit inspection request t...

Nov 29, 2010

Project Finishes

Forum Topic

Hi every body, i want to ask a question plz, i have 10 stories building, i want to plan for the finishes, i did the items for each floor , lets say : block work, plaster, partitions , falce ceiling, paint, water proofing, tiling, installing FF& E etc...

Nov 29, 2010

Budgeted Units issue from P3 TO P6

Forum Topic

Hi Planners, I have trasfered data from SAP to P3 then p3 to p6. I got everything except following: The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may caus...

Nov 29, 2010

TOPICS LOCKED

Forum Topic

Did not know which thread to post this on but here will do,Whats the craic with the "TOPIC LOCKED" on some threadsTrying to get some information relating to P6 and can't view posts Bring back the old PP!!

Nov 30, 2010

TOPICS LOCKED

Forum Topic

Did not know which thread to post this on but here will do,Whats the craic with the "TOPIC LOCKED" on some threadsTrying to get some information relating to P6 and can't view posts Bring back the old PP!!

Nov 30, 2010

Fed up with Primavera

Forum Topic

HI I wonder how many people out there have had enough of P6.  I have been around for many years using Artemis, Open Plan, MS Project and P3.  In my opinion there was nothing wrong with p3 except that primavera had mainly captured the project scheduli...

Nov 30, 2010

Project Man hours

Forum Topic

Hi Experts, To built a Refinery, ( regardless to Capacity)  how many Manhours required, for EPCM. we built a gas plant capacity was 20 million cubic meter per day, we use , approximate 6 million manhours for EPCM. Could any one share the , same infor...

Dec 1, 2010

P3 data saving before new updating

Forum Topic

Hi, What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule. Thanks in advance. Kannan

Dec 1, 2010

WBS in Primavera

Forum Topic

When I have a project with 30 buildings and the activities are pretty similar for all 30 buildings, I want the schedule to be done building wise, can I enter multiple activity / wbs codes for each activity or do I need to enter each activity 30 times...

Dec 1, 2010

Resource loading in P6

Forum Topic

Hi friends, I need to assign the same resource to all activities in P6 schedule. How it can be done using global change? Can anyone advise? Kannan

Dec 1, 2010

Benchmarking for scheduling standards

Forum Topic

Hi, I am working on research paper.Topic is benchmarking of scheduling practices.In this aim is to dvelop a list of cross checks or standards to check the quality of schedule.Any work can help me..where I can find: list of checks required to decide t...

Dec 1, 2010

Benchmarking for scheduling standards

Forum Topic

Hi, I am working on research paper.Topic is benchmarking of scheduling practices.In this aim is to dvelop a list of cross checks or standards to check the quality of schedule.Any work can help me..where I can find: list of checks required to decide t...

Dec 1, 2010

Benchmarking for scheduling standards

Forum Topic

Hi, I am working on research paper.Topic is benchmarking of scheduling practices.In this aim is to dvelop a list of cross checks or standards to check the quality of schedule.Any work can help me..where I can find: list of checks required to decide t...

Dec 1, 2010