When I have a project with 30 buildings and the activities are pretty similar for all 30 buildings, I want the schedule to be done building wise, can I enter multiple activity / wbs codes for each activity or do I need to enter each activity 30 times?
WBS in Primavera
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
if i understand your question well, you can insert activities for one building and then make (copy=>paste) with select ( Auto-increment ) from paste options
best regards
jihad aldaoud
Hello Manoj,
do you want to display the 30 or so buildings together, or one at a time?
you will enter all the activities once for each building with a specific activity code "Building" value for each building; or only once if you want to see only one building
however I cannot see the reason why you would like to display only one building; it seems more appropriate to enter all the 30 buildings, are possibly filter on one specific building
Alexandre