Recurring activity in P6
Forum TopicHi all, I need to put a recurring activity in a schedule to show a meeting which is scheduled every 6 weeks. Is this possible in P6, if so, can anyone tell me how to do it please? Many thanks.
Hi all, I need to put a recurring activity in a schedule to show a meeting which is scheduled every 6 weeks. Is this possible in P6, if so, can anyone tell me how to do it please? Many thanks.
Hi all P6 Users. White using activity usaege spreadsheet tab to calculate the monthly accumulative PV and Ev, I have encountered the following Problem.I hope someone can suggest the solution. Activity spreadsheet window- --> right click ---> spread...
Dear PP Friends I need your feedback in regards the following question What is the definition of Front loaded & Back Loaded Resource Curve. which resource curve will give correct progress status. To get the resource curve I have to load from global R...
Hi Tilll now i used the following macro to copy custom field content from the task tabelle to the assigment tabelle. So when i save the project it copy text5 from the gantt chart to text5 field in the ressource usage view. This macro does not work ...
Hi ; Anyone using TILOS for your Activity Movement Chart? Senthuran
Hey Guys,Just went to interview and the guy asked me a confusing question : tell me how you can pull out Critical path in a network?i already know about the backward and forward pass, total float and longest path, but i dont know what was in his mind...
i am currently working on a deep basement project for my university coursework and was wondering if someone could help me with a case study of deep basement construction shedule[ microsoft project]. dosent matter what type of building it is i just wa...
Friends While loading the resourses when I am entering the budgeted units the duration is changing ..wats the reason???Please help. RgardsArun.V
Friends While loading the resourses when I am entering the budgeted units the duration is changing ..wats the reason???Please help. RgardsArun.V
Hi everyone. I want to show the usual schedule and also the histogram in the same sheet I want to print in Primavera P6. Waiting for your comments.. Tomas
Hello, I'm new to Primavera and have been given the task of updating a plan in P6 but before i start i want to save the original on my desktop in case i make mistakes in the original that cannot be undone etc. Is it just a case of File, Save As and r...
Hi, guysI'm not good at MSP software.how can define a task that last from start of project to finish of project??I know that in p6, we can change the activity type to Level Of Effort, but What about MSP, how can I define this activity?? regardsShima
DearsI want to define some conditional relationships for an activity, for example, I have 2 activity that are predecessors of third one, I want to define these relationships as, if one of to these predecessors finished, the third activity could start...
Hi All We are about to conduct a forensic analysis for EOT entitlement, work is still in progress and one could probably say 'Time is at large' on the project.The only option seems to be Impacted vs as-planned for each change/delay event that has bee...
Hi, I am new to claims etc. I have been brought in on a project as a project planner, and i was given a copy on PDF of the original tender program - the person completing the tender has left the company and i have not got a software version of his pr...
When you are filling out the application form to write the PMP exam, they require you to summarize the project management tasks that you managed for each project you have listed. This description is between 300 and 550 characters. The project descrip...
Dear All, We are dredging co.,we have contract consists of 2 phases,the first to dredge up to -4m,the second to dredge up to -8m. Each phase has certain time and rate . During the 1st phase duration ,the owner instructed me to dredge up to -8 directl...
PMP Training Ahmedabad : Course Details: Objective: To prepare you for PMP Certification using Classroom and Online training To Learn World's Best Project Management practices based on PMI's PMBOK 4th Edition To help the participants in gaining the m...
I am using Primavera P6 and I have a plan in which I have split down to Daily, Weekly, Monthly, Quarterly, Six Monthly and Annually activities. I have the planned duration for each and I was wondering is there any need in putting a duration in if I h...
The Acumen team has released a new module for the Fuse platform which automatically generates optimized, accelerated schedule scenarios. Using criteria defined by the project team, including acceleration goals (i.e. accelerate the project by 3 months...