Resourse Loading

Friends 

While loading the resourses when I am entering the budgeted units the duration is changing ..

wats the reason???

Please help.

 

Rgards

Arun.V

S
Shah. HB 👤 Member for 17 years 6 months

Hi Arun Vasanth 

 

It is due to duration type you assigned to each activity try by using option fixed duration and units 

 

Cheers