% Complete Confusion - here is the data...
Forum TopicApril 29 Data Date April 29 Actual start on activity Orig Dur = 20 Actual Dur = 5 Rem. Dur = 20 Per. Complete Type = Dur. Dur. Complete = 0% Sched. % Complete = 45% - how is this possible.float -39.Should I tell the contractor it has to be wrong to h...