Ok, so there is an owner caused delay, say it is 30 days. So the Contractor gets a 30 day time extension and what % of Gen. OH costs = 4%, 6% of contract value - what is the general rule of thumb? I know there are 10 ways to calc it, what is most simple? what is most common? If there was a cost loaded schedule, couldn't they supercede that simply because accounting has better numbers or industry precedence?
Owner caused delay - most basic cost %?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts