I have 2 projects open with 2 different data dates. I am sliding a bar in the 2nd one but my Duration at completion is not coming out right - or to fix that the dates are not correct. I have checked the calendars - could it be because of the data dates? I don't see what that has to do with it but I don't know what else it could be. I tried it actualized in the future and un-actualized. mystery...it is not off by the difference in data dates....
I have 2 projects open with 2 different data dates.
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
I think the issue must have something to do with the Calendar "days" actually being hours - the cal. came from a contractor so not yet about it, but I sustpect. My 256 days slid 6 months does not match the dates of these 256 days later - per outside checks...
I think the issue must have something to do with the Calendar "days" actually being hours - the cal. came from a contractor so not yet about it, but I sustpect. My 256 days slid 6 months does not match the dates of these 256 days later - per outside checks...