Forum Topichi we are updaing the program on weekly basis - our cut off date is thursday shall i use data date ( friday) in primavera 6 or thursday ? thanks Alaa
hi we are updaing the program on weekly basis - our cut off date is thursday shall i use data date ( friday) in primavera 6 or thursday ? thanks Alaa
Hello I have a difficulty here. Hope I get an answer. Can anyone please suggest me how to insert a field in P6 'Group & Sort'. Check the attached snapshot below. I need to insert a field where the arrow mark is pointed. [[wysiwyg_imageupload:996:]] ...
Dear Scheduler,I need your help by send me a schedule P6 for Oil&Gas project to my E-Mail([email protected]) with my great thanks to you..Hanson
Hi Guys, From time to time, we come across projects that have two sponsors and we've written about some of the problems this causes here http://bit.ly/GVcxha Does anyone else come across this?Emily
Hello admins,I am still trying to understand where PlanningPlanet locates an answer to a post;* above all the existing posts,* bellow all the existing posts,* after the post that was selected when I saved my answerIt is very difficult to find the mos...
Awaiting your positive responses with referencce to above mentioned subject "Summarized PLanned & Actual % are showing above 100% i.e. 652 % & 546% in P6 .1 after updation. What is the reason, how to mitigate the issue. [[wysiwyg_imageupload:998:]]...
Hi I am using P6, i have following problemI have huge project with many activities, i want to add up duration of few consectivite activities , I have defined a dummy activity , assigned it a Level of effort activity type (LOE) , and assigned SS to Pr...
Freinds,Please suggest me how can I copy and paste resource usage spreadsheet from P6 to excel or export it to excel, considering that the type of resource is MATERIAL.
Hi all, I have inherited a program from a colleague which is based on 7day x 12hrs calendar. When i am adding durations and relationships into the program, they seem to be extending past the dates required. For example; Activity 1 = 2 days Activity...
Hi all, I have inherited a program from a colleague which is based on 7day x 12hrs calendar. When i am adding durations and relationships into the program, they seem to be extending past the dates required. For example; Activity 1 = 2 days Activity...
Hi all planners,I was studying Retained Logic and Progress Override options in P6. And understood well about Retained Logic also I understood that the result under Progress Override are not realistic. Then, the question raised that if the results are...
Hi I hope this is a simple problem that can be easily fixed!I have relationships to tasks in my project, however, when I set the task to started or finished, and then schedule the project, it seems to lose the relationship to the predecessor and seem...
Hi , Recently i have been migrating from MS projects to Primavera P6 Pro R8.1.I accidentally deleted all the projects instead of one. Since then i am not able to create new project, nor i am able to import any from MSP. Also the Projects menu is seen...
What is better - 6.7 or 8.2 and why / what are the differences? Thank you
Hi Everyone, I was wondering if there is any reason Planners as a whole arent on the Australian Skilled Occupation List? I cant find anything that would relate to planning on the skills list. http://www.immi.gov.au/skilled/_pdf/sol-schedule1.pdf I ...
Hi guys,I am new in Canada and not familiar with the ongoing rates for Planners and Schedulers Canada wide. I do know that it varies between provinces with Calgary being the highest. Would anyone be kind enough to post the rough brackets of reasonabl...
HiCan anybody guide me how to represent Cash Flow with P6 in Bar Chart & S Curve format.I check the option in tracking but it represent only Resources in S Curve format once choose Project Cost it shows in table form. Please guide me.Thanks
Introduction Microsoft Project -MSP- is a project management software developed by Microsoft. MSP is designed to help project managers in developing plans, tracking progress, managing the budget, assigning resources to tasks and analyzing workloads ....
Hi all,I have an issue with open ended tasks ina plan. I'm analysing the plan with Primavera risk analyser and the open ended tasks in the plan are lying on the critical path.What's the best way to deal with this, please? Get the master Primavera pla...
Dear Friends I use p6.7, oracle. when i try to add new project i recive this message: ""ORA-12952: The request exceeds the maximum allowed database size of 4 GB"" even when i delete some projects to find some space in my database, i still get the sam...