Hi
I am using P6, i have following problem
I have huge project with many activities, i want to add up duration of few consectivite activities , I have defined a dummy activity , assigned it a Level of effort activity type (LOE) , and assigned SS to Predessor and FF to successor ,
Now this dummy activity is summing up the duration , its fine , but its not summing up the budgeted costs . Its showing 0 cost.
Why is it soo...??????
Kindly help.
You would have to add the resource/cost to the Level of effort as well. The Level of effort is in itself another activity but doesnt work in the same way as a summary bar would in MS Project?
Hi,
Advices you to use the Activty Coding.