Forum TopicHow to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks,
How to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks,
We are making a schedule for a building with many contractual milestones which are given constraint "finish on" in P6. These milestones are linked with each other with FS relationship and lag 0. However, with this arrangement the schedule is not show...
Acumen is hosting their third annual user summit on Sept. 30 - Oct. 2 in Houston, TX. Join us for three days of networking, knowledge sharing, and learning for Acumen software users and project management professionals alike. This year's conference ...
Presently I am in Kuwait, please advise me that where I can get training and certification of Spider Project Professional in kuwait. Regards
Hi every one,I am preparing a Full Preparation Course for Planning Engineers, and i offer my course free of charge for whoever do not have money to pay the fees. And i made the course fees already very low rate (150 $) for those who can pay.Please ta...
Hello,I'm just wondering if there's a way to limit access to certain layouts when working on a project in a particular EPS node. E.g. I have different EPS Nodes for Client programmes, My programmes, and Subbie programes. I also have different layouts...
Dear all I had problem with the duration which i was working , there is what is diffrence between orignal and at copletion duration , how we can use it in primevera thanks you all
Planners,I work in the overhead line transmission industry, this mainly depends on client outages in order for us to carry out work.So basically as soon as an outage begins we can start work on the refurbishment of conductors etc, we have a set time ...
Not sure which category to place this under ... as it is definitely light-hearted ... but -- I have written a murder mystery about a Project Controls Director who kills his superior, the Vice President of Operations. It takes place in a construction ...
I just received the blast email (reprinted below) from PMI's Scheduling Community of Practice announcing the webinar that I will be doing for them on July 10th. It is FREE to all PMI members, but you have to register for it. Last I heard (about two w...
Dear AllI want to share my views and your comments as well. We have a new project manager after a gap of more than one month. The project at status the moment1- Progress percentage around 53%2- 13 months behind the schedule3- Project r...
Dear all,I am checking the work with portfolios.As far as I understand, the mechanism is as followsWhen you add project to portfolio and then consolidate projects, Spider considers all object except activities to be the same in different projects as ...
Hi Guys, I have got a problem with Earned Value Labor Units in one of my projects new activities, that Earned Value Labor Units is not getting calculated according to activity %. Please suggest the possible reason, to fix this error. Regards, Abi...
We have different labour rates in different financial years and we need to extract accurate time-phased costs from P6 (Release 7 SP4). The labour rates per financial year have been setup against the resource for the applicable time period. When we vi...
Hello I am trying to use the Estimate to complete (ETC) as my Labor Units for my resource loading histograms. However, when I go into my reports I am unable to create a report using ETC (only allows me to pick Remaining Units). Any suggestions? K
Here's asimple tutorial on how to use Work Products and Documents in Primavera P6 http://ow.ly/mmw34
Hi all,I am presently faced with the following issue:The supplier has submitted a MSP file to both me and another planner. However, when we open the file, both of us see different Project completion dates. Both our settings and file source being the ...
Hi folks is the there any equivalent to wbs summary (of primavera p6 ) in Ms Project 2007 ? if yes , how to to do it ? Regards Kamel
Hi folksis the there any equivalent to wbs summary (of primavera p6 ) in Ms Project 2007 ?if yes , how to to do it ?RegardsKamel
I have this problem at work: I have my time schedule which is updated up to data date, now a new area is going to be added to project scope which the engineering and construction activities have been started 2 months before. now thay ask me to prepar...