Import Multiproject Plan in P6 from MS Project

Forum Topic

Hi everyone.Well my question is the following...how i can import in P6 a multiproject plan from Microsoft Project?...I explain me, I have in MS Project a Project Plan conformed by 7 individuals projects plan (7 individual files) and linked by externa...

Dec 29, 2010

Unresolved Mystery of timing in P6

Forum Topic

I have a strange problem in my program. I have given a lag of 21 days. The predecessor activity is completing by Dear All, I have a strange problem in my program. The successor activity is starting on the same day, when predecessor activity is comple...

Dec 30, 2010

Error in Login - User already log on..

Forum Topic

Hi to All, I have experience some error in login to P6 as follows: I have regularly using the P6 client from a server and suddenly one day i got an error in login saying... "The user already log in..." What was the cause of it and How to resolve? Tha...

Dec 30, 2010

P6 Training in Doha

Forum Topic

Currently using P3 and feel like obsolete already. I would like to have training in P6 in Doha, Qatar. Anyone know good traininag centre? How much is the cost?

Dec 30, 2010

METRO STATION SCHEDULE

Forum Topic

Dear All,   Can anybody share  a construction schedule for the metro station construction.   Rohit

Dec 31, 2010

Conditional Scheduling

Forum Topic

I already worked out my first switch activity and works perfectly when using dates of the switch activity itself, but I would like to make the condition to compare field values of other activities. Say Switch activity code is 100 but would like to co...

Dec 31, 2010

Happy New Year 2011

Forum Topic

Dear PP Members, Wishing you a happy and prosperous 2011. Keep your planning clear and your schedules simple. With kind regards, Samer

Jan 1, 2011

Man Hour Planning

Forum Topic

Hi friends       I want to know the thumb rule for man power planning. For eample:- i am taking 35 hous for detail engineering for equipment design for A1 size, 72 Hous for stress analysis report and so on in my project .similarly i wnat to know the ...

Feb 18, 2011

2 Schedules in 1

Forum Topic

Hi, I need to have a management schedule which is basically 2 months delayed from a contractor schedule. The client requested for 2 schedule into 1 as the actual are the same. I am thinking on how to this using planned start or something like that. P...

Feb 18, 2011

Automating the Printing of Report Groups

Forum Topic

I am trying to create a Script that will create a group of PDF Tabloid Reports based on Gantt View. But in my attempt the script recorder did not recorded some of the necessary steps. I could select My Layout Template and my Print Templates the print...

Feb 18, 2011

Remaining Labour Unit Calculations

Forum Topic

Hi, Was trying to get the remaining labour units out. And as follows Budgeted Labour Units = 16,804,352 Earned Value Labour Units = 5,235,908 Actual Labour Units = 2,696 Remaining Labour Units = 13,151,437 How do I get Remaining Labour Units = Budget...

Feb 18, 2011

NonLabour Units

Forum Topic

Hi, I was trying to generate a non-labour units curve. HOwever, The actual non-labour units is 0, the activity is 100% complete. The remaining nonlabour units is 0, the budgeted nonlabour units is 1020.   Can I generate a earned non-labour untis or d...

Feb 18, 2011

MSP 2010: How to activate an inserted Page Break

Forum Topic

I love these office 2010  softwares, but MSP has the top! I managed to find how to insert a Page Break in the Gannt view (go to File Options and select it in "Commands not present in the Ribbon", add it in the personnalized Quick Acces Toolbar.) But ...

Apr 12, 2011

iPad Apps

Forum Topic

is there any iPad app for viewing or editing MSP files ??and  what apps you recomend for a planner ??

Apr 13, 2011

P 6 to MSP 2007

Forum Topic

Dear All, I have imported a project from P6 to MSP 2007. The import was successful. But I have noticed that the Summary tasks shows the durations in Days while the subtasks / activities are in Hours. Also the predessor linkages are the(activity numbe...

Apr 13, 2011

Primavera P6 new project problem

Forum Topic

Hello all.I am beginner user in p6 and I got a problem here.Recently I just deleted all sample projects which come along with pakage. Now the problem is that:I am trying to create new project but it does not appear to do so, Infact I have searched th...

Apr 13, 2011

Remaining Units

Forum Topic

Hello all,   any help would be greatly appreciated,   I have an activity on a 12 hour calendar, the Budgetted Labor Units on the activity is 1433 hours, with a Duration (days) of 30, the remaining Labor Units (on the Status Tab) reads 1433 as the act...

Apr 13, 2011

Format the timescale in P6

Forum Topic

Hi All,Could anyone help me to format the timescale of a project made in Primavera 6. Instead of January, February, March I would like to show Month 1, Month 2, Month 3, etc....Thanks in advance for your help.Regards,Jinny Johny

Apr 13, 2011

Help need with % pls

Forum Topic

Please I need help... I have just two activities "test 1" and "test 2", 100 days duration each. When I put 100 units in "Budget">"Budgeted amount", for the activity "test 1" it gives some STRANGE 52 units in "earned value" and "actual to date" even w...

Apr 14, 2011