P 6 to MSP 2007

R
Rohit K 👤 Member for 18 years 1 month

Dear All,

I have imported a project from P6 to MSP 2007. The import was successful. But I have noticed that the Summary tasks shows the durations in Days while the subtasks / activities are in Hours. Also the predessor linkages are the(activity numbers + period in hours).

How to change the time period from hours to days?

Rohit

R
Rohit K 👤 Member for 18 years 1 month

Dear Paul H,

Thank you, is there no other solution. I am looking for importing files from P6 to MSP.

Rohit

P
Paul Harris 👤 Member for 25 years 1 month

You have to overtype the durations with the day value.

Ther is an article on my web site under technical articles about importing Microsft Project files into P6 that may inteterest you:

http://www.eh.com.au/technical_papers.html

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au- a Primavera scheduling software resources site

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts