Format the timescale in P6

J
Jinny Johny 👤 Member for 18 years 6 months

Hi All,

Could anyone help me to format the timescale of a project made in Primavera 6. Instead of January, February, March I would like to show Month 1, Month 2, Month 3, etc....

Thanks in advance for your help.

Regards,

Jinny Johny

N
Neal Walsh 👤 Member for 18 years 8 months

Jinny Johnny,

You need to select  'show ordinal dates'  and set to Month.

 

Rgds

Walshy