Adjust S curve Y axis value
Forum TopicDear Team Member,Please advise in Primavera p6 (R8.3) from cost loaded schedule; how to adjust secondary axis value to 100% in S curve.Thank you,Masud
Dear Team Member,Please advise in Primavera p6 (R8.3) from cost loaded schedule; how to adjust secondary axis value to 100% in S curve.Thank you,Masud
Dear All,I have Created A programme in p6, resource is also loaded. some of the resources overloaded. i can see that in resourse usage profile. but i tried to level the resource using resource levelling wizard, but its not working. after resource lev...
i want Oracle database 10g Expresss Edition user name & password
Dear Sir or Madam, Im pleased to introduce myself as a member of "Acceleration" Management Company. We are currently looking for a Project planner in Oil & Gas Industry to create and make an expert evaluation of Planned installation Schedule of moder...
Hi,In P6, we have allocated budget at WBS level and created a user defined field to capture commitment cost.But the values entered in commitment column is not rolling over to WBSs up in the hierarchy.Anybody has come across such cases or resolution ...
It's FREE! (no login required)Why search the entire internet when you are looking for information related to Project Management? Why not search across only the top project management websites? “The Project Management Search Engine” does just that!!! ...
Hello,I am facing a problem in P6 R8.3. I want to re-use and assign existing links under predecessor/successor tab to another activities as well. After selecting existing link under predecessor/successor tab, when I click on assign then a pop-up wind...
HI,Can any please help how can I generate layout that displays activities which has either been due or overdue. Regards NC
If projects could be modeled with formulas, therefore we could make the WBS in a methodical way, and also put in relationship all disciplines of project management. These formulas exist, they are here: http://3d-wbs.blogspot.fr/2014/04/part-102-3d-wb...
Tne answer here: http://3d-wbs.blogspot.fr/2014/04/part-101-how-to-define-workpackages.html
Hi I am a new member and really need help! Could anyone tell me how to split or a Suspend a activity but still carry out work on sucesscessor activity at same time how to show this on a gantt. Thankyou in advance Rammy
We have a contractor who is using a sub project built onto our main project schedule. Our data date is a month different from theirs (theirs being a month behind ours). When looking at the critical path and you accept relationships from other projec...
A discipline is not a Product, a task is not an activity, a system is not a component, etc.All the tree structures of projects are linked and you can see how here: http://3d-wbs.blogspot.fr/2014/05/part-103-3d-wbs-tree-structures.html
Hi,I have requirements for P6 where we need to implement functionality as below: Tracking changes and user engagement in processes shall be performed automatically by the application, thereby providing enhanced visibility and control to maintain comp...
Hi All, Just having a discussion on a recent schedule for a program I am working on, where an activity did not occur and has now been highlighted as a miss from the WBS. It is involved cycle development of piece of equipment. The standard WBS we use ...
Hi, Was after peoples thoughts on the best way to publish a programme (in Asta), without having to create a pdf (the people wanting to view it don't have Asta) for each view, each time there is a change. Chris.
So I am running into an issue with having Syncro load multiple databases at once. Currently everytime I switch to a different project I have to go and Configure Syncro to see the new project database (each project is in a different database). Is ther...
Dear Planners,How to update schedule in MSP, I mean whatever the percentage you enter for tasks, the completion date is not changed anymore, not like Primavera?Regards,Moutaz