Dear Planners,
How to update schedule in MSP, I mean whatever the percentage you enter for tasks, the completion date is not changed anymore, not like Primavera?
Regards,
Moutaz
Dear Planners,
How to update schedule in MSP, I mean whatever the percentage you enter for tasks, the completion date is not changed anymore, not like Primavera?
Regards,
Moutaz
Dear planners,
I rescheduled my project, the new finish time change when I update project. how can I update rescheduled project in MSP?
Best regards,
hasanzadeh
Thanks Li,
This way is manually updated, it does not make sense, what I need is; the schedule should be automatically updated once the actual dates and percentage complete are entered.
Regards,
Moutaz
I can share some ways that I always use . i am a new guy to MSP,but you can have a try.
after you typing into the percentage in the complete coloum , you can add another coloum called "remain duration", and type into you estimated remain duration. the finish date will change.