Showing "day of the week" in separate column next to date
Forum TopicHi,Does anyone know if it is possible to show the day of the week associated with a date in P6V7 preferably in a separate column to the date ?ThanksBob
Hi,Does anyone know if it is possible to show the day of the week associated with a date in P6V7 preferably in a separate column to the date ?ThanksBob
hai friends i'm new to this site. please help me with your advices i'm a beginner in mep planning. but i have no experience in the whole mep systems. the only experience i have is in sprinkler systems. but now i'm forced to study and do the planning ...
7 scheduling mistakes to avoid http://ow.ly/kFT2h
How to make a fragnet of activities in primavera P6? What exactly does the word "fragnet" mean in this context? The fragnet is supposed to consist of subset of activities in the project schedule directly related to the schedule. Fewest number of ac...
I guess I'm getting impatient in my old age. I'm used to the very intuitive way MSP allows you to insert tasks, and then insert subtasks by indenting. And being able to drag things around. From the P6 manual and the web, I cannot figure out how to di...
Dear All,I am faced with a problem.I have created a programs and have given the cost for each activity as a Resource "Cost". The cost values was given in "Budget cost" column. It was all fine when I did the programs and the "Budgeted Total Cost" was ...
There is some topic regarding changing the start/finish date with in the programme with global change, but I can`t find. Programme has actual and keep all information regarding previous baseline (P6-programme is without attached baseline) I need to r...
Hi Asta Management In a recent discussion Stephen Devaux wrote this sentence: I know you are very active with Asta, and in light of your remark above, I feel I must ask: if Asta wants to incorporate modern technology and metrics, why doesn't it inclu...
If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract ...
Hi All, I'm just about to start on the 'adventurous' task of building my own house and I want to create a WBS for the entire build. Does any one have a WBS structure for a building a house or could point me in the right direction to find one. Thanks ...
Not that I haven't done it before but I wanna have some discussion on how planners load quantities / cost from BOQ. I am currently studying on how to optimize the use of P6 in terms of valuation / claims / time extension cost impact etc...I would rea...
Hello, Recalling from P3 that were able to create a native P3 file from a filtered layout, wonder if possible to do the same in P6. May be infront of the eyes and not able to see. Do not want to go to the path of deleting unwanted activities and th...
Urgently need help; I did a latest update for bi-weekly reporting , after my updation i assigned the baseline & found out that the earned value cost for two activities which are 100% complete does not replect in earned value column only the actual co...
in projects layout(Primavera6),where i used different codes in organization my projects,is there any way that i can show the number of projects under each branch(automaticly)? I tried to use user defined fields (Integer) and give value =1 to each pr...
Why is that some people say: you can not use Physical percent complete on this schedule because it is not resource-loaded ?As far as I know, Physical percent complete for the activities has nothing to do with the cost,except for calculation of WBS pe...
I am normally using Primavera, but am curently in an organisation using MS Project 2012 (+server). I have suggester to start link activities between projects, but the other planners in the org. claims, that MSP cannot handle this....! Statement from ...
Can anyone help me with my problem? I have this updated program and I want this to return to the original program which is not updated yet. If it has 15000 activities and 12000 are already on progress. Is there any short cut that will make it unupdat...
ALL,Can anyone help me how to keep the activity dates fixed. Everytime i press the F9 some dates are automatically adjusting on their own. I have to replot each activities again and again. I'm all done with the putting dates and relationships then wh...
Hi,I have an activity that is showing as critical with zero float (total float and free float) that shouldn't be .... all of it's sucessors have at least 1 day float on them, it has no constraints, the planned start and finish, remaining early start ...
Hello folks, I'm new to the site and have a few questions that you may be able to help me with. I would like to enter the scheduling field, but I'm not sure what my best route of attack should be to get there. I'm currently a regional safety manager ...