Earned Value Cost not appering on update once baseline assigned!

Urgently need help;

I did a latest update for bi-weekly reporting , after my updation i assigned the baseline & found out that the earned value cost for two activities which are 100% complete does not replect in earned value column only the actual cost is appearing, so after the baseline assigning the budget at completion is different from at completion total cost, ...what happened, i need your help?