Multiple NEC contracts one project

M
Matt Hunt 👤 Member for 16 years 3 months

If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract and hence additional costs as his whole contract period has moved as a block

M
Mike Testro 👤 Member for 20 years 5 months

Hi Matt

Contractor B would be entitled to an extension of time - shifting the work period to a later date is an EoT.

But then if Contractor A had both contracts then delays on one contract would entitle Contractor A to an EoT on the other.

This is true even if the first delay was not a compensation event.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts