Predecessors and Successors in same row of report in P6
Forum TopicHello guys, I am creating a new report in Primavera P6 (R 8.2) and the format I'm looking for is as below:Activity id Activity name Predecessor name Successor name1 Activi...
Hello guys, I am creating a new report in Primavera P6 (R 8.2) and the format I'm looking for is as below:Activity id Activity name Predecessor name Successor name1 Activi...
My client asked me to prepare a recovery schedule because we are in short negative -5% from the planned value.Now what my client want is that my recovery curve should cross/match the baseline curve as soon as possible & further more it must be up/ahe...
Hi! I am having a problem with Visualizer Layout.Pic 1) In schedule Comparison, I was comparing two projects, but those projects were no longer needed so I deleted it. After that, I wanted to compare other projects in the same layout(point-2 in pic),...
Etan started in 2011 as EMR Analyst and now serves Chief Operating Officer for Allied Physicians Group, a premier primary care independent physician group with over 30 locations throughout the New York metropolitan area, as well as, Board Member of t...
I deleted the EPS in Primavera 15.1, where primavera accepted to delete all nodes, now I have no records in the EPS, it is completely empty.How can I create a new one if the add button (+) is not available and Primavera doesn't allow to add any new E...
Anyone have a schedule for an oil metering skid from engineering, fab, transport install and commission?Interested in seeing the detailed activities that occur Thanks
In the following figure I have some distributed data shown but I need to disclose which parameters on the leyend. How it is done?
In the IPA approach, if the owner assembles the project team without regard to any pre-existing relationships among team members, how can the owner successfully select a primary participant contractor? What are the best practices (tested) criterias o...
Hi all,First post on here and I am a QS so go easy on me! (Admin feel free to move this message if I have posted it in the wrong area). I'm a freelance QS and rather disillusioned with my career. I spent the first couple of years of my career working...
Hi, My activities' % Complete Type is set to "Physical". I enter physical progress of the activities, however the earned values do not change. If i enter duration progress e.g remaining duraiton or labor hours, the earned value change. My question ...
These two videos illustrate how fast it is to prepare resources, roles and all of their information in Excel and export them as XER file directly to Primavera.This is the first video to prepare the resources from completed projects and current projec...
Hi Everyone,In my project i have some activities that can't be executed with delay, the second activity is modeled imediatly after first activity. For this reason I set "strict" on this activities.After scheduling, the report below show me this infor...
Question about insurance liability - this one is only tangently related to our usual schedule items. I am looking at the “value” at bid time of the owner moving from a cap on liability for the contractor comparing 100% of the contract price on liabil...
Greetings PlannersI am updating a baseline schedule, some of the activities that have actual start but not yet completed, their bar after the data date bar is not continous, there is a space between the data date and then the bar for the next period ...
When viewing the primavera Gant chart, the shaded columns representing non-wokring days have become a very light shade of grey and extremly difficult to see.Is there a way to revert them to the original color? or darken the exisiting color?
Hello All, I am a Project Control Engineer in Oil & Gas Sector. I keep on hearing SAP requirement in Planning in some companies. Does anyone have an idea of what it is related to and what course needs to be done. I am in UAE. Reccomendation much appr...
If I contractor is really delayed 10 days in say June, on a two year project, but then is able to work 10 more days in that following December than the assumption in the schedule, should they still get those 10 days of delay? If not, why would anyon...
I want to confirm something.Lets say we have 1000 lf of conduit to install. One labor installs 200 lf conduits a day. Lets call him worker 1. So it will take him 5 days to complete.Now if we had only him as labor, the duration of this task is 1000/20...
When a successor is complete 100% the program just skps to the next successor in the chain, so why should the logic be changed to the way it really happened? Or should we just leave it to keep from complicating the schedule and comparisons? I used ...
Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems? - These items are intertwined - one of the worst things you can do is make the schedule into either a submittal log (or a to do list). But how to you eff...