Recovery Schedule with Additional Manpower

I
Irfan Khan 👤 Member for 16 years 10 months

My client asked me to prepare a recovery schedule because we are in short negative -5% from the planned value.

Now what my client want is that my recovery curve should cross/match the baseline curve as soon as possible & further more it must be up/ahead then the baseline s-curve unless you reach between 90% to 95%.

In addition client wants to show the more manpower requirement than the baseline planned manpower.

Here what I did, I crushed the schedule & tried to get all the results as my client want, but one thing I couldn’t understand that if my Budgeted Manhours are fixed then how would I show him the more required manpower then baseline.

Let say if I changed/increased the budgeted manhours to the activities where I need more manpower so my overall actual (which I am calculating from Earned Value Labor Units) will be changed.

any good advise in this regard will be highly appriciated

thanks in advance.....!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts