Primavera P6 and Listing On Budget Status
Forum TopicHere's a tip on how to use a Primavera P6 UDF field to list the on budget status of each activity http://ow.ly/iu8i30doC83
Here's a tip on how to use a Primavera P6 UDF field to list the on budget status of each activity http://ow.ly/iu8i30doC83
The contract contains multiple unit completion penalty milestones which are waived if the final completion milestone is achieved. The project is in serious delay. The contractor has submitted an EOT claim (TIA and owner delay events only) that is foc...
I am dealing with complex project that seems to be growing arms and legs and as such there has been slippages and delays to the programme. Can anyone give me advice on how best to analyse this? I would like to carry out some detailed analysis and to...
HiiiiiI want help for the plllllaneeers ... I can't update the duration schudle for this WBs . How do we can to this ???[[wysiwyg_imageupload:4876:]]
[[wysiwyg_imageupload:4877:]]After updating & scheduling the program for weekly progress my manager asked me to show him the update, he particularly pointed out that the finish date of activity "Node 1 to 2 Bedding" (selected in screenshot) is not re...
For years I have been involved in trying to fill planning and scheduling positions for our clients, and am left with a few enduring questions as a result:1. Is it really so hard to train and retain an in-house capability, such that this skill needs t...
Here's how to display an activity late bar on the Gantt chart to help better understand schedule flexibility http://ow.ly/99yr30duYD2
Hi,I have a schedule with milestone activities that are complete but are showing only 0% complete. It is only happening to some of the milestone activities and not others. Percent complete type is Physical, its a start Milestone and both started an...
Here's a great tip on how to insert a milestone and constraint in Microsoft Project to highlight the importance of material delivery and document slippage accountability http://ow.ly/DaFZ30dxa4z
Dear planners , Help me make cash flow for 7 month villa project I have boq , contract and job order , please guide me asap. Sample templates will be thankful .
Hello, I'm looking for some help on the Resource Usage Profile, When I look at the Resource Usage Profile in P6, it looks like this...as it should[[wysiwyg_imageupload:4882:]]However when I print the profile the figures are mixed up, and looks like ...
Hi all,Does anyone have an idea why one schedule activity, assigned the same resource as all other schedule activities, would show a 'Budeted Total Cost' as the amount divided by 4? (I can tell it's divided by 4 because the SDEF file shows the correc...
I received a scedule update using performance % complete in a schedule without resources. Does that make any sense? Isn't performance percent complete related to EVM? How can P6 show PPC when there are no resources in the schedule?Thank you
HelloIs there any way that when the data date is moved on and progress is updated that the earned value at previous period end remains fixed at what it was. For example, an activity that was 90% complete at year end will always have 90% earned at tha...
Here's how to isolate or unmask the true longest path from among multiple critical or non-critical float paths in support of schedule compression http://ed.gr/cgvi
I am new to the P6 and would really appreciate if someone can answer my queriesi) Is there any guideline on how to determine productivities for the labour and non-labor resources? ii) How does the apply actuals option work for starters? iii) I know i...
Dear experts/MikePlease mention the steps that 1) How to hide bar under shaded timescale?2) How to show the full summary bar instead of break in summary?Please see snapshot for 1 and 2 : http://ge.tt/3OBWrnl2I used all options but no success.I tried ...
I am updating my program on a weekly basis. Since my project is late my milestone dates are being delayed. The maximum delay for each milestone compared to the previous update should not exceed 7 days (since I am updating on a weekly basis). However,...
I am updating my program on a weekly basis. Since my project is late my milestone dates are being delayed. The maximum delay for each milestone compared to the previous update should not exceed 7 days (since I am updating on a weekly basis). However,...
Currently our company are trying to upgrade Primavera P6 EPPM v7.4 to v15.2 or v16 (using Microsoft SQL database) because it hard to find Primavera P6 consultant in our area, my management ask me to do the upgrading process. I am not an IT guy. So d...