Is there any way that when the data date is moved on and progress is updated that the earned value at previous period end remains fixed at what it was. For example, an activity that was 90% complete at year end will always have 90% earned at that date.
Thanks in advance.
thats if you are using physcial % complete
I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.
I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.
after the update is totally done select tools store period performance
make sure to set up your financial periods
I have been advised to do this but when the data date is advanced and the activities progressed the earned value at previous periods is still changed.
tools store period performance