I have a schedule with milestone activities that are complete but are showing only 0% complete. It is only happening to some of the milestone activities and not others. Percent complete type is Physical, its a start Milestone and both started and finished boxes are ticked (actualized).
when you say showing 0% complete is that physical or duration % complete
look at the duration type what is it ?