Search

P330XER Converter Tool

Forum Topic

Hello, I am having an issue converting P3 to Xer. The conversion tool provided "P330XERConverter" when ran has the "P3" option greyed out. THe only thing left to choose is SDEF. Any reason this would be happening? The file is located on the same mach...

Mar 19, 2014

Project Suspend Activity

Forum Topic

Hi to All,I need help, Im using P6 ver 8.2.  Ive read some of the forums regarding using the calendar, its advantages and disadvatanges on this problem.Heres the situation, Project operation was suspended for 60 days due to a Tower Crane Collapse.Que...

Mar 20, 2014

Project Finish becomes Early Finish After Scheduling.

Forum Topic

Ok, this is baffling me. The schedule is a month behind where we should be, so i try to reflect this accurately within the programme, and this doesnt want to play ball, the Logic within these activities is sound. Activity X - Submit Document A, Finis...

Mar 20, 2014

Introduction info could be better

Forum Topic

I have just went through an unplanned shutdown where we did complete a lot of work for an upcoming planned shutdown but more could have been done. I just joined but there is no guidance for newcomers for either searching forums or posting questions (...

Mar 22, 2014

Resources

Forum Topic

Dear all, Currently been tasked with detailing the resources we require as the isolating department. Upcoming shutdown is a fairly varied work scope involving several different plant systems. We only have 3 technicians per shift. Our onshore focal po...

Mar 22, 2014

Spider Project Wikipedia article is created

Forum Topic

Dear all,I wanted to try to write a Wikipedia article for quite a while, and I decided to start with Spider Project.It took me 2 months to have it reviewed and approved, but now it is finally formally published.https://en.wikipedia.org/wiki/Spider_Pr...

Mar 22, 2014

New, New, New

Forum Topic

It has been suggested that we create a new section for discussion on this huge sector / topic.We hope it helps.Keep on Planning...

Mar 22, 2014

PLEASE HELP...WBS activities won't show !!!

Forum Topic

I have created a new WBS with actives. But when I close up the entire project (log of from P6) and then re-open up the project id, the WBS i showing without it's actives on. Have gone to Group and Sort to un tick Hide if empty, but still didn't help ...

Mar 22, 2014

The right way to update as a sub contractor

Forum Topic

Dear AllI have one question here. we as a sub contrauctor, using a whole program along with main contractor and other sub contractors (Baseline issued to us is the program issued by Engineer for the whole project including main contractor and all sub...

Mar 22, 2014

Activity % Complete in Totals and Sub-totals do not appear

Forum Topic

Hi Planning Experts,Currently I am updating my programme in P6. My programme is resource loaded with manpower and material. In updating I am using Activity % complete in the column and physical % as the percent type. But after updating there I cannot...

Mar 24, 2014

Cost overrun

Forum Topic

Dear All I am working on a project which started 2012 & finish date is 2019, Mining project. I prepared the project & got all cost variance as per planned & actual with delay analysis. Now we need to find the [strong]cost overrun [/strong]compare wit...

Mar 24, 2014

BL Project Finish not matching BL Project Early Finish

Forum Topic

I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates 1. How can I correct this so my BL Project Finish dates match the BL Project ...

Mar 24, 2014

Assigning Critical Path Manually !

Forum Topic

Hi everybody .. Is it OK to choose certain activities and make them critical instead of just relying on P6 critical path calculation using total float or longest path? Why we should do this? and finally what is the best teqnique to do so?  Thanks in ...

Mar 25, 2014

Budgeted units unable to edit

Forum Topic

I couldn't able to edit Budgeted units or Remaining units in Resource assignments window. However same can be done in Resource usage spreadsheet. Why? How to overcome this?I logged in with full rights (both admin superuser & project superuser). I use...

Mar 26, 2014