How to make activity % complete and Schedule % complete
Forum Topic
Hi, Anybody can tell me how to cast a column in top down construction after the higher floor slab casted? Thanks.
Hello, I am having an issue converting P3 to Xer. The conversion tool provided "P330XERConverter" when ran has the "P3" option greyed out. THe only thing left to choose is SDEF. Any reason this would be happening? The file is located on the same mach...
Hi to All,I need help, Im using P6 ver 8.2. Ive read some of the forums regarding using the calendar, its advantages and disadvatanges on this problem.Heres the situation, Project operation was suspended for 60 days due to a Tower Crane Collapse.Que...
Ok, this is baffling me. The schedule is a month behind where we should be, so i try to reflect this accurately within the programme, and this doesnt want to play ball, the Logic within these activities is sound. Activity X - Submit Document A, Finis...
Hi,I have developed a project plan (which includes a % complete and a % planned column) and I wish to insert 3 types of indicators to show me how I am advancing with the progress of each activity: Green: Shows the activity is on targetYellow: Shows t...
I have just went through an unplanned shutdown where we did complete a lot of work for an upcoming planned shutdown but more could have been done. I just joined but there is no guidance for newcomers for either searching forums or posting questions (...
Dear all, Currently been tasked with detailing the resources we require as the isolating department. Upcoming shutdown is a fairly varied work scope involving several different plant systems. We only have 3 technicians per shift. Our onshore focal po...
Dear all,I wanted to try to write a Wikipedia article for quite a while, and I decided to start with Spider Project.It took me 2 months to have it reviewed and approved, but now it is finally formally published.https://en.wikipedia.org/wiki/Spider_Pr...
It has been suggested that we create a new section for discussion on this huge sector / topic.We hope it helps.Keep on Planning...
I have created a new WBS with actives. But when I close up the entire project (log of from P6) and then re-open up the project id, the WBS i showing without it's actives on. Have gone to Group and Sort to un tick Hide if empty, but still didn't help ...
Dear AllI have one question here. we as a sub contrauctor, using a whole program along with main contractor and other sub contractors (Baseline issued to us is the program issued by Engineer for the whole project including main contractor and all sub...
Hi Planning Experts,Currently I am updating my programme in P6. My programme is resource loaded with manpower and material. In updating I am using Activity % complete in the column and physical % as the percent type. But after updating there I cannot...
Hi Planning Experts,How can I generate a tabular data from an S-curve generated in P6?Thanks.Arvin
Dear All I am working on a project which started 2012 & finish date is 2019, Mining project. I prepared the project & got all cost variance as per planned & actual with delay analysis. Now we need to find the [strong]cost overrun [/strong]compare wit...
I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates 1. How can I correct this so my BL Project Finish dates match the BL Project ...
Hi everybody .. Is it OK to choose certain activities and make them critical instead of just relying on P6 critical path calculation using total float or longest path? Why we should do this? and finally what is the best teqnique to do so? Thanks in ...
Here's an article that explains the Primavera P6 Project Status Field http://ow.ly/uWfNT
its like im having an existing schedule then ive decided to add more activities and rearrange the sequence...unfortunately the Acitivity IDs were no longer arrange in an ascending order, since i already change the sequence, how can i rearrange them i...
I couldn't able to edit Budgeted units or Remaining units in Resource assignments window. However same can be done in Resource usage spreadsheet. Why? How to overcome this?I logged in with full rights (both admin superuser & project superuser). I use...