Dear all, Currently been tasked with detailing the resources we require as the isolating department. Upcoming shutdown is a fairly varied work scope involving several different plant systems. We only have 3 technicians per shift. Our onshore focal point has voiced doubts that we can provide the required isolations in the current time frame suggested. Manpower itself is not an issue as we can use the maintenance and construction personnel as muscle but the control of the isolations will be hard to manage. Any tips on how to efficiently manage valve tagging on this scale etc would be great. We have very tight controls for minor PPM type isolations but these will have to be relaxed slightly to speed equipment preparation. Also any idea on how I should try and workout isolation timings as the big hitter is the flare system with approx 500 isolation items and no guarantee all tie in valves will hold. Any help on estimations would be a great boon to us. Thanks for reading and please advise if you can Best regards Mark
Resources
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Moved to STO forum
Mark,
My involvement in shutdown jobs have been very limited but still there are some scheduling issues I would like to share.