Budgeted units unable to edit

I couldn't able to edit Budgeted units or Remaining units in Resource assignments window. However same can be done in Resource usage spreadsheet. Why? How to overcome this?

I logged in with full rights (both admin superuser & project superuser). I used only "Fixed Duration & units" as duration type.

Can somebody help? Thanks.

P
Parthiban Sekar 👤 Member for 13 years 3 months

The software used is Primavera P6R8.3.

Hi David,

Usually with fixed duration & units also it is possible to manually edit the budgeted units in Resource assignments window. (this is future period bucket planning as I understood)

and there is no duration type like fixed duration in Primavera

 

D
David Craig 👤 Member for 16 years 7 months

Perhaps if you change it to just fixed duration, then you may be able to edit the units?

You can then change back to fixed duration and units once you have edited the units.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts