Budgeted units change with budgeted cost

Forum Topic

Hello, i have a question. My old company used to use $1/Unit for money tracking, and never used expenses. My new company i just started with only used expenses for tracking money as required by the customer. I loaded the schedule using expenses as re...

Jan 29, 2016

Resource Analysis Help - Microsoft Project 2013

Forum Topic

Hello!I 'm hoping someone here will be amiable to helping me get the data I'm looking for out of Microsoft Project. I'm not really looking for another software solution at this time (though, I'll definitely be browsing at the CPM Conference next week...

Jan 29, 2016

The Last Planner System

Forum Topic

I am doing a research on the implementation of the Last Planner System on construction sites for my Undergraduate dissertation. May you please take some time and fill in this 5 minute questionnaire. Thank you.http://www.smartsurvey.co.uk/s/Q5W3C/ 

Feb 1, 2016

M09-5 - Project Performance Forecasting - EVM

Forum Topic

RE: GPCCAR on EVM09.0 - MANAGING PROJECT PROGRESS - 09.5.3.2 THE PERIODIC PROGRESS REPORT - STEP 7: OPTION 2: REJECT THE PROGRESS UPDATE AND REQUIRE A RE-BASELINE BE PREPAREDIn the event that the project as being built is “materially” or “significant...

Feb 2, 2016

Projected As Built - New Delay Analysis Method.

Forum Topic

Projected As BuiltA New Delay Analysis Method This is a condensation of my 25 years experience as a Delay Analyst into one simple system.It Requires:No critical path - no detailed weekly as built data - no detailed logic - can be used by any junior p...

Feb 2, 2016

Project Updates using P6 Team Member

Forum Topic

We are considering using P6 Team Member for undertaking regular field level project updates. Will appreciate if anyone can share their experience in using P6 Team Member.

Feb 2, 2016

Tracking Revenue & Dealing with Changes

Forum Topic

Hi, Currently we track revenue [what we can claim from the client] by assigning a  value loaded Non-Labour Resource to each activity, this is fine for measuring individual values per activity, but for overheads [Security/Welfare etc..] we assign them...

Feb 2, 2016

New rates for 2016 - P6 recalcuating prior actuals

Forum Topic

Hi All, we've updated our rates per resource ID by adding the new rates with an effective date of 1st Jan 2016. For activities that are not yet complete the prior actuals, which have been stored in period performance, are being recalculated at an ave...

Feb 2, 2016

New Baseline

Forum Topic

Hi All, I have had to change budgeted hours from my scedule i have had to take out nearly a third,  Should i now make a new baseline ?  If i do when should i do new baseline after next update etc? Kind Regards Leighton

Feb 3, 2016

calculate budgeted units

Forum Topic

Dear FriendsQ:1-I am Newbee.I completed B.tech in civil Eng in 2013.i join as a planning engg in gulf region directly.so i dont have site engg experience.what i will do gain the knowledge in site as welll as planning. is there any book or i have to g...

Feb 3, 2016

Total Number Of Projects

Forum Topic

Hi All,How can show the total number of portfolio's project in p6Imean without exporting to excel .  Thanks

Feb 3, 2016

Check in and Check out

Forum Topic

Hi all,anyone can explain to me functionality of check in and check out in p6 and the benfits of using   Thanks

Feb 4, 2016

Manhours Factor

Forum Topic

Hello Everyone,Just to clarify a point. For a construction project on what logic is the manhours calculated. For example the manhours for ,DiciplineUnitQuantityManhoursPipingDia Inch19.67 This includes the workforce starting from the foreman to do th...

Feb 4, 2016

Non-repetitive calendar patterns

Forum Topic

Hello everyone, This is my first post on this forum so please forgive me for destroying forum rules. My question is is there anyway to build a pattern in calendar? Like 2 days work 1 day holiday or nonworking day after 8 days of working. Maybe making...

Feb 4, 2016

Project Update

Forum Topic

After setting up the first baseline what steps are necessary to update the project i.e only updating the duration or the the update status of resources are necessary? and how do i compare the progress of my project?

Feb 4, 2016

Project Update

Forum Topic

After setting up the first baseline what steps are necessary to update the project i.e only updating the duration or the the update status of resources are necessary? and how do i compare the progress of my project?