Manhours Factor

Hello Everyone,

Just to clarify a point. For a construction project on what logic is the manhours calculated. For example the manhours for ,

DiciplineUnitQuantityManhoursPipingDia Inch19.67

 

  • This includes the workforce starting from the foreman to do the work to the helper (Direct Manpower). This gives the weightage of the perticular dicipline ie as per the quantity of manhours used per dicipline.
  • It does not include the hours of equipment used (Crane to lift the pipe and hold) - but include the hours of the operators who runs the equipment.

Could you say if the logic is correct ie,

  • Manhours = Hours of Personals used to do the Work
  • Manhours = Hours of Personals used to the Work + Equipment Hours used to do the Work.

Warm Regards

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

 

Hi Rashid and Johannes,

Thank you for your input.

I usually keep Direct Manpower to calculate the Weightage per dicipline or activity, which includes all the personal working under supervisors like the foreman, technician , helper, equipment (JCB, Crane etc) operators, etc.


But I dont use the Equipment (JCB,Crane etc) hours to do the weightage calculation ie it wont be included in the Manhour calculation for each task.

Regards

Jithin

R
Rashid Iqbal 👤 Member for 16 years 2 months

Jithin,

1. Manhours are manhours and equipment hours are equipment hours; they shoudl be kept separate. The reasons is this when you will do the PF report then the earned hrs should be compared with the manhours incurred (timesheets coded to that work).

2. Most companies consider Foreman hrs as direct but please check it in your porjects estimate as where the Foreman and General Foreman hrs have been accounted.

 

Regadrs

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Thanks Mike,

So when you say " Manhours = Hours of Personals used to the Work + Equipment Hours used to do the Work ".

and its not " Manhours = Hours of Personals used to do the Work " - which is the total hours of personal required to do one Unit of the Work (which includes all Labor, Technician, Operators of Crane etc)

So inorder to get this table the Manhours should include "Personal hours used to do the work + Equipment Hours used to do the work"

Dicipline Manhours Weightage %
Civil 68353 42.42%
Structural 13864 8.60%
Mechanical 6930 4.30%
Piping 61804 38.36%
Electrical 5542 3.44%
Instrumentation 4640 2.88%
Total 161132 100%

Just for clearing it up Example : " The Pipe is not on the trench it would be above ground" which would require crane to hold it up whith the joining pipe so as to weld.

Warm Regards

Jithin

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jithin

The usual procedure is to set up a composte gang resource including all the time cost related resources.

Then select 1 resource as the output driver - in this case the welder - which comprises the time for each of the 3 weld phases per inch diameter plus 2 20 minutes cooling time.

This is then converted to 1 weld per 18 m of pipe which is then converted to an hourly output of xm per hour.

If you are using automatic welding then the output would be much quicker.

BTW - the crane doesn't hold the pipe when it is being welded - the pipe is laid alongside the trench and then clamped into the next pipe for welding. The cranes then side lift the welded pipe length (1km) into the trench.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts