Float increasing in successor activities (P6)

Forum Topic

I am in the process of reviewing a schedule wherein the activities have large float. The first problem I am seeing is that the float is increasing in the successor activities. For example, the first few activities have 187 days of float, the next ser...

Apr 18, 2011

Primavera P6v7 to TILOS

Forum Topic

I would like to request a step-by-step guide on how to prepare data from Primavera P6v7 to be impoerted to Tilos...Thanks!

Apr 19, 2011

ENGINEERING MANAGEMENT

Forum Topic

  Physical progress for the engineering phase of a project consists of three levels of indenture as follows: Progress by drawing Progress by discipline Total engineering progress Drawing Milestones   Start draft  (20%)Layout and design completed and ...

Apr 19, 2011

Event Code PDF

Forum Topic

Hai Do anyone of us have PDF all the Event Code Error in P6 & Soultion for that Respectively or if  any know  any Event Code No & Solution for it can you post it here   Regards Anbin

Apr 19, 2011

P6 Calendar - modify work hours

Forum Topic

Hi Planners, I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the ...

Apr 20, 2011

P6 Calendar - modify work hours

Forum Topic

Hi Planners, I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the ...

Apr 20, 2011

P6 Calendar - modify work hours

Forum Topic

Hi Planners, I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the ...

Apr 20, 2011

Acvity Complete and Activity Step Complete

Forum Topic

Hello Fellow Planners,   I was wondering if the activity steps are linked to activity complete at all?   In order to clarify my question, I would like to give an example: If my activity has 3 steps (same weight assumed-> 0,33) and I check one step as...

Apr 20, 2011

Acvity Complete and Activity Step Complete

Forum Topic

Hello Fellow Planners,   I was wondering if the activity steps are linked to activity complete at all?   In order to clarify my question, I would like to give an example: If my activity has 3 steps (same weight assumed-> 0,33) and I check one step as...

Apr 20, 2011

Updating Actual Units and using curve to spread remaining units.

Forum Topic

I am using P6, Labour resources, Bell Shaped Curve and fixed Duration & Units to resource load my schedule however, I have now been given Actual spent hours to update some activities.  If I change Duration Type to Fixed to update actual, P6 does not ...

Apr 20, 2011

UPDATING Over 1000 activities

Forum Topic

How long will it take to update 1000 activities for example. if done manually. From my experience and calculationIf in  30 secs -------- 1 activity         1 min --------- 2 activities     500 mins--------- 1000 activitiesSo 500 mins is abt 8h 40mins...

Apr 20, 2011

Use of Differnt Calenders P6

Forum Topic

Hi All, I wonder if you can help using p6.7, have put together schedule but have used two different calenders within the schedule. One calender a Ten day fortnight 9 hr working time the other 7 day calender working 12 hr days.   On the activities usi...

Apr 20, 2011

Use of Differnt Calenders P6

Forum Topic

Hi All, I wonder if you can help using p6.7, have put together schedule but have used two different calenders within the schedule. One calender a Ten day fortnight 9 hr working time the other 7 day calender working 12 hr days.   On the activities usi...

Apr 20, 2011

Use of Differnt Calenders P6

Forum Topic

Hi All, I wonder if you can help using p6.7, have put together schedule but have used two different calenders within the schedule. One calender a Ten day fortnight 9 hr working time the other 7 day calender working 12 hr days.   On the activities usi...

Apr 20, 2011

Baseline Schedule/Provisional Package

Forum Topic

Hi guys! Can i call your great minds attention? i have a schedule to be prepared with the following scenarios: 1. Package 1 has a duration of 2 years from NTP issue. 2. Package 2 may or may not be instructed to do so, however, if it will be included ...

Apr 20, 2011

Duration at Completion

Forum Topic

When I have an activity with 1 resource assigned P6 changes the assignment to the max number of units for that resource.  Why?  The max level for a resourse is 15 so when I put in an activity with 1 resource it changes to 15.  If it has 2 resources i...

Apr 20, 2011

Duration at Completion

Forum Topic

When I have an activity with 1 resource assigned P6 changes the assignment to the max number of units for that resource.  Why?  The max level for a resourse is 15 so when I put in an activity with 1 resource it changes to 15.  If it has 2 resources i...

Apr 20, 2011

Project Control Manager Required - Aberdeen, Scotland

Forum Topic

1. Ten years minimum experience in:   * Project schedule Management * Project cost Management * Project risk Management * Contract Management * Procurement Management * Human Resource Management   2. Five years minimum experience in managing a projec...