Spam messages
Forum TopicThere seems to be a lot of spamming messages these days. I delete them when I find them, but it is quite time consuming and onerous. What is the procedure for blocking users who post spam?
There seems to be a lot of spamming messages these days. I delete them when I find them, but it is quite time consuming and onerous. What is the procedure for blocking users who post spam?
Cannot we manipulate the reports generated in MSP 2007? If so yes how can we, cause I am getting errors and states that it cannot be done. Request to revert back on this querry Rohit
I know in the previous versions of PPM (v6 and older), WBS or Act Codes summary uses the default calendar if activities under it uses different calendar IDs. In P6.7, is there a way now to control what calendar we want the group summary to use in co...
Does anyone know of a way to display the whole WBS title, other than by expanding the width of the first column to show it. Is there a button that I have missed in the setup of a layout? Regards Roger
Hi, For cost monitoring we decided to record actual cost especially against material. On a demo project I loaded some material on various activities and to record actual cost I unchecked both “Auto compute Actual” and “Calculate costs from units” be...
Hello,i am new on this forumi have to build a WBS for a construction project including design and procurementi don't know exactly where to insert the shop drawing in my WBS, and how to develop the constrcution phase,here is my proposition, if somebod...
Hello to all,I am trying to find out why a certain dialog box appears right after I login to P6. So, the P6 "Login to Primavera P6" dialog box comes up on starting the program. I plug in my password, and the the login dialog box title changes to "...
Dear all, Hello, I want to suggest making a place in the web site to upload and download files between members. Thanks Samer SalmaSenior Planning EngineerKCT
Hi all, When i try to re-schedule me program (F9) i get the following error; "PROJ Environment Variable is too long " Anybody no how i resolve this issue as i cant re-schedule until its done! Thanks in advance Mike
Sir' are ther any video tutorial using project 2010 or 2007 to make delay analysis thanks
Hi there,Could someone please help me? I need to import an old programme in Excel spreasheet format into P6. I've got that error message that "The User Preferences used to create this Excel file could not be found. Importing this file could corrupt y...
Just would like to find out can you set the earned value calculations to use resource units? ev=units vs time. if yes where do i change this, or can you only base the earned value as ev= cost vs time.
Just would like to find out can you set the earned value calculations to use resource units? ev=units vs time. if yes where do i change this, or can you only base the earned value as ev= cost vs time.
Hi PP Admin We are getting a lot of new members reviving long dead threads - they seem to search a topic and then pitch in regardless of when the last message was posted. Spammers seem to be doing this quite a lot. Can we have a system whereby a thre...
I am looking for a way to display on a diagram the values of available resource workloads distribution. For example by looking at the following table we will see that for Day 3 or D3 that there are 2 resources A available 100 of their time, 2 resourc...
Scheduling is the process of deciding how to commit resources between a variety of possible tasks and often refers to the creation of a time or resource schedule.
Project Controls relates to the use of systems and is that element of a project that keeps it on-track, on-time and within budget.
Cost Engineering is concerned with the application of techniques encompassing cost estimating, cost control, profitability analysis, project management, relating to the planning and scheduling of projects. Cost Engineers are similar to those of Quan...
Hi As an occassional user of Microsoft i have a query Is there any way of setting up week numbers ie period numbering options from a specific date ie project start date Any help is appreciated Thanks Regards [Topic moved to MSP forum by G...
Dear, I have the following questions. milestones to be linked with a final milestone necessarily? I am doing a Schedule that when linked the final milestone milestones and critical path shows only the final milestone, despite the fact that there are ...